Datacenter Sites in Harnett County, North Carolina
Harnett County has 41 scored datacenter candidate sites averaging 53.9/100 DC Readiness, with a catalogued aggregate of 6,800 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
41
Candidate sites
53.9/100
Avg DC Readiness
6,800 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Harnett County
Yessales_tax_exemption
Datacenter tax incentive
11.12¢/kWh
Commercial electricity
7.80¢/kWh
Industrial electricity
10
Fiber providers
Low
Water stress
$6,229
Land price / acre
1,600
Cooling degree days
3,300
Heating degree days
59°F
Mean annual temp
Incentive detail: Sales tax exemption on DC equipment and electricity for $75M+ investments; property tax abatement.
By site type
Top datacenter sites in Harnett County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| TAP147408 | Substation-Adjacent | 230 kV | 300 MW | 4.3 yrs | 68.8 |
| UNKNOWN113996 | Substation-Adjacent | 230 kV | 300 MW | 4.3 yrs | 67.0 |
| UNKNOWN115253 | Substation-Adjacent | 230 kV | 300 MW | 4.3 yrs | 66.7 |
| UNKNOWN113998 | Substation-Adjacent | 230 kV | 300 MW | 4.3 yrs | 65.9 |
| TAP147189 | Substation-Adjacent | 230 kV | 300 MW | 4.3 yrs | 65.8 |
| UNKNOWN115252 | Substation-Adjacent | 230 kV | 300 MW | 4.3 yrs | 65.7 |
| TAP147191 | Substation-Adjacent | 230 kV | 300 MW | 4.3 yrs | 65.1 |
| UNKNOWN113993 | Substation-Adjacent | 230 kV | 300 MW | 4.3 yrs | 65.1 |
| UNKNOWN114119 | Substation-Adjacent | 230 kV | 300 MW | 4.3 yrs | 65.0 |
| ERWIN | Substation-Adjacent | 230 kV | 300 MW | 4.3 yrs | 64.7 |
| UNKNOWN113999 | Substation-Adjacent | 230 kV | 300 MW | 4.3 yrs | 64.1 |
| TAP147192 | Substation-Adjacent | 230 kV | 300 MW | 4.3 yrs | 64.0 |
| TAP147670 | Substation-Adjacent | 230 kV | 300 MW | 4.3 yrs | 62.2 |
| TAP160791 | Substation-Adjacent | 115 kV | 100 MW | 4.3 yrs | 61.6 |
| TAP147673 | Substation-Adjacent | 230 kV | 300 MW | 4.3 yrs | 61.3 |
| TAP147190 | Substation-Adjacent | 230 kV | 300 MW | 4.3 yrs | 60.8 |
| UNKNOWN113511 | Substation-Adjacent | 230 kV | 300 MW | 4.3 yrs | 60.7 |
| UNKNOWN113997 | Substation-Adjacent | 230 kV | 300 MW | 4.3 yrs | 60.5 |
| UNKNOWN114110 | Substation-Adjacent | 115 kV | 100 MW | 4.3 yrs | 59.1 |
| Greenfield (CUMBERLAND - WAKE) | Greenfield | 500 kV | 1,000 MW | 4.3 yrs | 57.9 |
| UNKNOWN113994 | Substation-Adjacent | 115 kV | 100 MW | 4.3 yrs | 55.0 |
| Greenfield (TAP147190 - FAYETTEVILLE EAST) | Greenfield | 230 kV | 300 MW | 4.3 yrs | 53.2 |
| OZ Harnett | Greenfield | — | — | 4.3 yrs | 53.1 |
| EC Coal Harnett County | Greenfield | — | — | 4.3 yrs | 51.6 |
| OZ Harnett | Greenfield | — | — | 4.3 yrs | 51.4 |
Harnett County datacenter FAQ
- How many datacenter sites are in Harnett County?
- 41 scored datacenter candidate sites, averaging 53.9/100 DC Readiness.
- Does Harnett County offer datacenter tax incentives?
- Sales tax exemption on DC equipment and electricity for $75M+ investments; property tax abatement.
- What is the natural-hazard risk in Harnett County?
- FEMA's National Risk Index rates Harnett County as "Relatively High" (score 42).
- What are industrial electricity rates in Harnett County?
- Average industrial electricity is 7.80¢/kWh and commercial is 11.12¢/kWh in Harnett County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Harnett County, North Carolina. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.