UNKNOWN134080

Substation-Adjacent

Cavalier County, North Dakota · SPP

DC Readiness
68.8
Good / 100

UNKNOWN134080 is a substation-adjacent datacenter candidate site in Cavalier County, North Dakota, interconnecting through SPP. It screens at 68.8/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 1.4 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN134080
Substation distance0.0 mi
Substation voltage115 kV
Available capacity100 MW
LMP zoneSPP_NORTH
Wholesale LMP$21.13/MWh
Utility commercial rate0.07¢/kWh

Speed to power

ISO / RTO regionSPP
Queue depth9
Avg queue wait1.4 yrs
Recent queue wait1.4 yrs
Completion rate20%
Withdrawal rate80%

Connectivity

Nearest IXPMidco Grand Forks
IXP distance84.7 mi
Fiber providers4
Fiber coverage100.0%
Nearest cloud providerGCP
Nearest cloud regionus-central1
Cloud region distance534.2 mi

Site characteristics

Parcel ownerSlaubaugh, Ronald W. & Dorothy A.
Parcel APN10347000
Land owner typeprivate
Buildability60.0/100

Risk & environment

Flood zoneZone X
Water stress (WRI)1.00
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score80/100
Construction cost index77.9 (avg 100)

Location context

Nearest datacenterMidco Grand Forks
DC distance84.7 mi
Nearest rail2.1 mi
Nearest gas pipeline1.1 mi
Nearest fiber route51.4 mi
County hazard (FEMA NRI)Relatively Low (20)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity7.24¢/kWh
Industrial electricity7.57¢/kWh
Cooling degree days500
Heating degree days8,600
Land price / acre$2,507

Incentive detail: Property tax exemption for new DC construction for up to 5 years.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
56
Speed to power15%
66
Fiber connectivity12%
73
Energy cost10%
91
Water risk8%
80
Natural hazard8%
80
Buildability7%
60
Labor market4%
50
DC cluster4%
20
Land / acreage3%
52
Construction cost3%
85
Gas pipeline2%
97
Tax incentive2%
100
Climate / cooling2%
100

Nearby comparable sites

Other scored datacenter candidate sites in Cavalier County, ranked by DC Readiness.

Sites near UNKNOWN134080
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN134103Substation-Adjacent115 kV100 MW1.4 yrs69.1
UNKNOWN134096Substation-Adjacent115 kV100 MW1.4 yrs68.5
UNKNOWN134083Substation-Adjacent115 kV100 MW1.4 yrs68.5
UNKNOWN134102Substation-Adjacent115 kV100 MW1.4 yrs65.4
Greenfield (UNKNOWN134096 - UNKNOWN134546)Greenfield115 kV100 MW1.4 yrs64.3
EC Coal Cavalier CountyGreenfield1.4 yrs63.5
Greenfield (UNKNOWN134096 - UNKNOWN134546)Greenfield115 kV100 MW1.4 yrs63.1
Greenfield (UNKNOWN134101 - TAP155892)Greenfield115 kV100 MW1.4 yrs62.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for UNKNOWN134080, Cavalier County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.