EC Coal Belmont County

Greenfield

Belmont County, Ohio · PJM

DC Readiness
60.2
Good / 100

EC Coal Belmont County is a greenfield datacenter candidate site in Belmont County, Ohio, interconnecting through PJM. It screens at 60.2/100 DC Readiness and a 3.2 yrs average interconnection-queue wait.

Power & interconnection

LMP zonePJM_AEP
Wholesale LMP$41.99/MWh
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth9
Avg queue wait3.2 yrs
Recent queue wait4.4 yrs
Completion rate17%
Withdrawal rate83%

Connectivity

Nearest IXPLSTI 401 Market
IXP distance51.5 mi
Fiber providers7
Fiber coverage21.1%
Nearest cloud providerGCP
Nearest cloud regionus-east5
Cloud region distance64.1 mi

Site characteristics

Site typeGreenfield
Parcel ownerConservation Fund Th
Parcel APN12-90006.001
Land owner typeprivate
Buildability95.0/100
Land cover (NLCD)Developed, Medium Intensity
Former usecoal mine

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Present
Critical habitatClear
Superfund nearbyClear
Hazard sub-score60/100
Construction cost index88.1 (avg 100)

Location context

Nearest datacenterLSTI 401 Market
DC distance51.5 mi
Nearest rail10.9 mi
Nearest gas pipeline4.1 mi
Nearest fiber route18.2 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.33¢/kWh
Industrial electricity9.40¢/kWh
Cooling degree days900
Heating degree days5,400
Land price / acre$4,446

Incentive detail: DC sales tax exemption on equipment and electricity (2022 law); JobsOhio grants.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
51
Fiber connectivity12%
48
Energy cost10%
91
Water risk8%
90
Natural hazard8%
60
Buildability7%
95
Labor market4%
50
DC cluster4%
50
Land / acreage3%
48
Construction cost3%
77
Gas pipeline2%
87
Tax incentive2%
100
Climate / cooling2%
80

Nearby comparable sites

Other scored datacenter candidate sites in Belmont County, ranked by DC Readiness.

Sites near EC Coal Belmont County
SiteTypeVoltageCapacityQueue waitScore
Greenfield (UNKNOWN151647 - KAMMER (765KV))Greenfield765 kV1,000 MW3.2 yrs68.3
Greenfield (UNKNOWN151647 - KAMMER (765KV))Greenfield765 kV1,000 MW3.2 yrs68.3
Greenfield (UNKNOWN151647 - KAMMER (765KV))Greenfield765 kV1,000 MW3.2 yrs67.5
GLENCOESubstation-Adjacent138 kV100 MW3.2 yrs66.9
Greenfield (KAMMER (765KV) - SOUTH CANTON )Greenfield765 kV1,000 MW3.2 yrs66.8
NEFFSubstation-Adjacent138 kV100 MW3.2 yrs66.6
UNKNOWN163629Substation-Adjacent138 kV100 MW3.2 yrs65.7
TAP171319Substation-Adjacent138 kV100 MW3.2 yrs64.5

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for EC Coal Belmont County, Belmont County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.