Licking County, Ohio · PJM

DC Readiness
66.4
Good / 100

TAP151048 is a substation-adjacent datacenter candidate site in Licking County, Ohio, interconnecting through PJM. It screens at 66.4/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.2 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTAP151048
Substation distance0.0 mi
Substation voltage138 kV
Available capacity100 MW
LMP zonePJM_AEP
Wholesale LMP$41.99/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth9
Avg queue wait3.2 yrs
Recent queue wait4.4 yrs
Completion rate17%
Withdrawal rate83%

Connectivity

Nearest IXPWēConnect Westerville
IXP distance24.7 mi
Fiber providers8
Fiber coverage37.7%
Nearest cloud providerAWS
Nearest cloud regionus-east-2
Cloud region distance25.3 mi

Site characteristics

Parcel ownerBlatter Farms Ltd
Parcel APN07333068400002
Land owner typeprivate
Buildability45.0/100
Land cover (NLCD)Deciduous Forest

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score70/100
Construction cost index95.0 (avg 100)

Location context

Nearest datacenterMeta
DC distance13.2 mi
Nearest rail1.6 mi
Nearest gas pipeline0.5 mi
Nearest fiber route25.4 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.38¢/kWh
Industrial electricity10.12¢/kWh
Cooling degree days900
Heating degree days5,400
Land price / acre$8,946

Incentive detail: DC sales tax exemption on equipment and electricity (2022 law); JobsOhio grants.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
58
Speed to power15%
51
Fiber connectivity12%
65
Energy cost10%
84
Water risk8%
94
Natural hazard8%
70
Buildability7%
45
Labor market4%
50
DC cluster4%
95
Land / acreage3%
40
Construction cost3%
71
Gas pipeline2%
98
Tax incentive2%
100
Climate / cooling2%
80

Nearby comparable sites

Other scored datacenter candidate sites in Licking County, ranked by DC Readiness.

Sites near TAP151048
SiteTypeVoltageCapacityQueue waitScore
JUG STREETSubstation-Adjacent345 kV600 MW3.2 yrs74.2
Greenfield (JUG STREET - KIRK)Greenfield345 kV600 MW3.2 yrs70.8
Greenfield (TAP141206 - WEST MILLERSPORT)Greenfield345 kV600 MW3.2 yrs70.0
Greenfield (UNKNOWN151647 - KAMMER (765KV))Greenfield765 kV1,000 MW3.2 yrs69.9
Greenfield (UNKNOWN151647 - KAMMER (765KV))Greenfield765 kV1,000 MW3.2 yrs69.6
Greenfield (UNKNOWN151647 - KAMMER (765KV))Greenfield765 kV1,000 MW3.2 yrs69.5
Greenfield (JUG STREET - KIRK)Greenfield345 kV600 MW3.2 yrs68.8
Greenfield (CORRIDOR - CONESVILLE STATION)Greenfield345 kV600 MW3.2 yrs68.6

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP151048, Licking County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.