Van Wert County, Ohio · PJM

DC Readiness
68.8
Good / 100

HAVILAND is a substation-adjacent datacenter candidate site in Van Wert County, Ohio, interconnecting through PJM. It screens at 68.8/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.2 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationHAVILAND
Substation distance0.0 mi
Substation voltage138 kV
Available capacity100 MW
LMP zonePJM_AEP
Wholesale LMP$41.99/MWh
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth9
Avg queue wait3.2 yrs
Recent queue wait4.4 yrs
Completion rate17%
Withdrawal rate83%

Connectivity

Nearest IXPMicrotronix Datacenter Ottoville
IXP distance8.8 mi
Fiber providers8
Fiber coverage54.6%
Nearest cloud providerAWS
Nearest cloud regionus-east-2
Cloud region distance105.5 mi

Site characteristics

Parcel ownerStuckey Robert E
Parcel APN150384160000
Land owner typeprivate
Buildability65.0/100
Land cover (NLCD)Cultivated Crops

Risk & environment

Flood zoneZone A (SFHA)
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score55/100
Construction cost index69.1 (avg 100)

Location context

Nearest datacenterMicrotronix Datacenter Ottoville
DC distance8.8 mi
Nearest rail7.8 mi
Nearest gas pipeline0.2 mi
Nearest fiber route87.5 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.78¢/kWh
Industrial electricity8.59¢/kWh
Cooling degree days900
Heating degree days5,400
Land price / acre$9,658

Incentive detail: DC sales tax exemption on equipment and electricity (2022 law); JobsOhio grants.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
58
Speed to power15%
51
Fiber connectivity12%
78
Energy cost10%
91
Water risk8%
90
Natural hazard8%
55
Buildability7%
65
Labor market4%
50
DC cluster4%
85
Land / acreage3%
39
Construction cost3%
92
Gas pipeline2%
99
Tax incentive2%
100
Climate / cooling2%
80

Nearby comparable sites

Other scored datacenter candidate sites in Van Wert County, ranked by DC Readiness.

Sites near HAVILAND
SiteTypeVoltageCapacityQueue waitScore
R.P.MONESubstation-Adjacent345 kV600 MW3.2 yrs73.9
Greenfield (UNKNOWN133414 - EAST LIMA SUBS)Greenfield345 kV600 MW3.2 yrs71.9
Greenfield (UNKNOWN133414 - EAST LIMA SUBS)Greenfield345 kV600 MW3.2 yrs70.7
OZ Van WertGreenfield3.2 yrs66.2
Greenfield (NORTH DELPHOS - HAVILAND)Greenfield138 kV100 MW3.2 yrs65.4
Greenfield (NORTH DELPHOS - HAVILAND)Greenfield138 kV100 MW3.2 yrs65.2
OZ Van WertGreenfield3.2 yrs63.9
Greenfield (R.P.MONE - ROBISON PARK (345 K)Greenfield345 kV600 MW3.0 yrs63.4

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for HAVILAND, Van Wert County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.