Datacenter Sites in Beckham County, Oklahoma
Beckham County has 33 scored datacenter candidate sites averaging 61.8/100 DC Readiness, with a catalogued aggregate of 8,400 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
33
Candidate sites
61.8/100
Avg DC Readiness
8,400 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Beckham County
Yessales_tax_exemption
Datacenter tax incentive
8.79¢/kWh
Commercial electricity
5.95¢/kWh
Industrial electricity
4
Fiber providers
Low-Medium
Water stress
$1,768
Land price / acre
1,900
Cooling degree days
3,600
Heating degree days
60°F
Mean annual temp
Incentive detail: Sales tax exemption on DC equipment; 5-year ad valorem tax exemption.
By site type
Top datacenter sites in Beckham County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| BORDER | Substation-Adjacent | 345 kV | 600 MW | 3.4 yrs | 71.6 |
| UNKNOWN159874 | Substation-Adjacent | 345 kV | 600 MW | 3.4 yrs | 71.2 |
| ELK CITY | Substation-Adjacent | 230 kV | 300 MW | 3.4 yrs | 68.9 |
| UNKNOWN168526 | Substation-Adjacent | 230 kV | 300 MW | 3.4 yrs | 68.7 |
| UNKNOWN118502 | Substation-Adjacent | 230 kV | 300 MW | 3.4 yrs | 67.4 |
| TAP149238 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 66.1 |
| Greenfield (CHISHOLM - UNKNOWN159874) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 65.5 |
| UNKNOWN168528 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 64.9 |
| UNKNOWN118729 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 64.5 |
| TAP149752 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 64.2 |
| TAP149750 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 64.2 |
| UNKNOWN118728 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 64.2 |
| UNKNOWN118730 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 63.9 |
| Greenfield (WOODWARD - BORDER) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 63.7 |
| Greenfield (CHISHOLM - UNKNOWN159874) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 63.6 |
| Greenfield (WOODWARD - BORDER) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 63.5 |
| TAP149749 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 63.4 |
| UNKNOWN163665 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 63.3 |
| Greenfield (CHISHOLM - UNKNOWN159874) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 63.3 |
| Greenfield (CHISHOLM - UNKNOWN159874) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 62.9 |
| Greenfield (ELK CITY - CHISHOLM) | Greenfield | 230 kV | 300 MW | 3.4 yrs | 62.8 |
| UNKNOWN118726 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 62.7 |
| TAP149748 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 62.5 |
| Greenfield (UNKNOWN118502 - UNKNOWN168526) | Greenfield | 230 kV | 300 MW | 3.4 yrs | 62.5 |
| Greenfield (UNKNOWN118502 - UNKNOWN168527) | Greenfield | 230 kV | 300 MW | 3.4 yrs | 61.9 |
Beckham County datacenter FAQ
- How many datacenter sites are in Beckham County?
- 33 scored datacenter candidate sites, averaging 61.8/100 DC Readiness.
- Does Beckham County offer datacenter tax incentives?
- Sales tax exemption on DC equipment; 5-year ad valorem tax exemption.
- What is the natural-hazard risk in Beckham County?
- FEMA's National Risk Index rates Beckham County as "Relatively High" (score 42).
- What are industrial electricity rates in Beckham County?
- Average industrial electricity is 5.95¢/kWh and commercial is 8.79¢/kWh in Beckham County.
Dataset updated . Screening estimates derived from public data sources.