Datacenter Sites in Blaine County, Oklahoma
Blaine County has 24 scored datacenter candidate sites averaging 57.3/100 DC Readiness, with a catalogued aggregate of 4,800 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
24
Candidate sites
57.3/100
Avg DC Readiness
4,800 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Blaine County
Yessales_tax_exemption
Datacenter tax incentive
9.44¢/kWh
Commercial electricity
5.91¢/kWh
Industrial electricity
2
Fiber providers
Low-Medium
Water stress
$2,025
Land price / acre
1,900
Cooling degree days
3,600
Heating degree days
60°F
Mean annual temp
Incentive detail: Sales tax exemption on DC equipment; 5-year ad valorem tax exemption.
By site type
Top datacenter sites in Blaine County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| ROMAN NOSE | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 66.6 |
| UNKNOWN173344 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 66.4 |
| Greenfield (TATONGA - MATHEWSON) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 66.3 |
| Greenfield (TATONGA - MATHEWSON) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 66.3 |
| UNKNOWN118882 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 65.9 |
| Greenfield (TATONGA - MATHEWSON) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 65.5 |
| TAP173345 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 64.1 |
| Greenfield (TATONGA - MATHEWSON) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 63.5 |
| SOUTHARD | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 62.7 |
| Greenfield (ROMAN NOSE - TAP173345) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 60.9 |
| Greenfield (TATONGA - MATHEWSON) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 60.2 |
| Greenfield (TATONGA - MATHEWSON) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 60.1 |
| Greenfield (ROMAN NOSE - SOUTHARD) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 60.1 |
| Greenfield (ROMAN NOSE - SOUTHARD) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 59.8 |
| Greenfield (DARLINGTON ROAD - TAP173345) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 58.4 |
| Greenfield (UNKNOWN118424 - UNKNOWN118882) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 58.3 |
| OZ Blaine | Greenfield | — | — | 3.5 yrs | 58.1 |
| Greenfield (DEWEY - SOUTHARD) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 57.8 |
| Greenfield (ROMAN NOSE - EL RENO) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 54.6 |
| Watonga Armory | Industrial | — | — | — | 42.0 |
| Jones Farris F166 | Industrial | — | — | — | 41.8 |
| The Corner in Okeene | Industrial | — | — | — | 41.6 |
| Mine Site | Former Mine | — | — | — | 37.2 |
| Mine Site | Former Mine | — | — | — | 36.4 |
Blaine County datacenter FAQ
- How many datacenter sites are in Blaine County?
- 24 scored datacenter candidate sites, averaging 57.3/100 DC Readiness.
- Does Blaine County offer datacenter tax incentives?
- Sales tax exemption on DC equipment; 5-year ad valorem tax exemption.
- What is the natural-hazard risk in Blaine County?
- FEMA's National Risk Index rates Blaine County as "Relatively High" (score 42).
- What are industrial electricity rates in Blaine County?
- Average industrial electricity is 5.91¢/kWh and commercial is 9.44¢/kWh in Blaine County.