Datacenter Sites in Lake County, Oregon
Lake County has 80 scored datacenter candidate sites averaging 49.4/100 DC Readiness, with a catalogued aggregate of 36,500 MW. FEMA rates local natural-hazard risk as "Relatively Low". The county has a datacenter tax incentive on record.
80
Candidate sites
49.4/100
Avg DC Readiness
36,500 MW
Catalogued capacity
theoretical aggregate
Relatively Low
Hazard rating
Site-selection context for Lake County
Yesproperty_tax_exemption
Datacenter tax incentive
8.99¢/kWh
Commercial electricity
8.63¢/kWh
Industrial electricity
3
Fiber providers
Medium-High
Water stress
$2,108
Land price / acre
300
Cooling degree days
4,700
Heating degree days
49°F
Mean annual temp
Incentive detail: Enterprise Zone property tax exemption for 3-15 years; no sales tax in Oregon.
By site type
Top datacenter sites in Lake County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| FORT ROCK | Substation-Adjacent | 500 kV | 1,000 MW | 1.7 yrs | 65.5 |
| SUMMER LAKE | Substation-Adjacent | 500 kV | 1,000 MW | 1.7 yrs | 64.0 |
| SYCAN | Substation-Adjacent | 500 kV | 1,000 MW | 5.7 yrs | 62.8 |
| Greenfield (CELILO - SYLMAR EAST) | Greenfield | 1000 kV | 1,000 MW | 5.8 yrs | 60.8 |
| Greenfield (CELILO - SYLMAR EAST) | Greenfield | 1000 kV | 1,000 MW | 5.8 yrs | 60.6 |
| Greenfield (CELILO - SYLMAR EAST) | Greenfield | 1000 kV | 1,000 MW | 5.8 yrs | 60.5 |
| Greenfield (CELILO - SYLMAR EAST) | Greenfield | 1000 kV | 1,000 MW | 5.8 yrs | 59.7 |
| Greenfield (SYCAN - FORT ROCK) | Greenfield | 500 kV | 1,000 MW | 1.7 yrs | 59.5 |
| Greenfield (SUMMER LAKE - FORT ROCK) | Greenfield | 500 kV | 1,000 MW | 1.7 yrs | 59.3 |
| Greenfield (SUMMER LAKE - FORT ROCK) | Greenfield | 500 kV | 1,000 MW | 1.7 yrs | 58.6 |
| MILE-HI | Substation-Adjacent | 115 kV | 100 MW | 5.7 yrs | 58.6 |
| Greenfield (SYCAN - FORT ROCK) | Greenfield | 500 kV | 1,000 MW | 1.7 yrs | 58.5 |
| Greenfield (CELILO - SYLMAR EAST) | Greenfield | 1000 kV | 1,000 MW | 5.8 yrs | 58.3 |
| TAP208707 | Substation-Adjacent | 115 kV | 100 MW | 1.7 yrs | 58.1 |
| Greenfield (SYCAN - SUMMER LAKE) | Greenfield | 500 kV | 1,000 MW | 1.7 yrs | 58.1 |
| Greenfield (CELILO - SYLMAR EAST) | Greenfield | 1000 kV | 1,000 MW | 5.8 yrs | 58.1 |
| Greenfield (CELILO - SYLMAR EAST) | Greenfield | 1000 kV | 1,000 MW | 5.8 yrs | 58.0 |
| Greenfield (SUMMER LAKE - BURNS) | Greenfield | 500 kV | 1,000 MW | 1.7 yrs | 57.9 |
| Greenfield (CELILO - SYLMAR EAST) | Greenfield | 1000 kV | 1,000 MW | 5.8 yrs | 57.9 |
| Greenfield (SUMMER LAKE - BURNS) | Greenfield | 500 kV | 1,000 MW | 1.7 yrs | 57.4 |
| Greenfield (SUMMER LAKE - BURNS) | Greenfield | 500 kV | 1,000 MW | 1.7 yrs | 57.3 |
| Greenfield (SUMMER LAKE - BURNS) | Greenfield | 500 kV | 1,000 MW | 1.7 yrs | 57.0 |
| Greenfield (CAPTAIN JACK - SYCAN) | Greenfield | 500 kV | 1,000 MW | 1.7 yrs | 56.9 |
| Greenfield (CELILO - SYLMAR EAST) | Greenfield | 1000 kV | 1,000 MW | 5.8 yrs | 56.9 |
| Greenfield (SUMMER LAKE - BURNS) | Greenfield | 500 kV | 1,000 MW | 1.7 yrs | 56.8 |
Lake County datacenter FAQ
- How many datacenter sites are in Lake County?
- 80 scored datacenter candidate sites, averaging 49.4/100 DC Readiness.
- Does Lake County offer datacenter tax incentives?
- Enterprise Zone property tax exemption for 3-15 years; no sales tax in Oregon.
- What is the natural-hazard risk in Lake County?
- FEMA's National Risk Index rates Lake County as "Relatively Low" (score 22).
- What are industrial electricity rates in Lake County?
- Average industrial electricity is 8.63¢/kWh and commercial is 8.99¢/kWh in Lake County.
Dataset updated . Screening estimates derived from public data sources.