Datacenter Sites in Jasper, South Carolina
Jasper has 30 scored datacenter candidate sites averaging 62.0/100 DC Readiness, with a catalogued aggregate of 4,316 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
30
Candidate sites
62.0/100
Avg DC Readiness
4,316 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Jasper
Yessales_tax_exemption
Datacenter tax incentive
11.87¢/kWh
Commercial electricity
8.11¢/kWh
Industrial electricity
10
Fiber providers
Low
Water stress
$4,579
Land price / acre
2,000
Cooling degree days
2,400
Heating degree days
63°F
Mean annual temp
Incentive detail: Sales tax exemption on DC equipment; fee-in-lieu of property tax for $50M+ investments.
By site type
Top datacenter sites in Jasper
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| UNKNOWN167524 | Substation-Adjacent | 230 kV | 300 MW | 3.7 yrs | 71.3 |
| UNKNOWN170159 | Substation-Adjacent | 230 kV | 300 MW | 3.7 yrs | 69.6 |
| JASPER | Substation-Adjacent | 230 kV | 300 MW | 3.7 yrs | 69.2 |
| TAP167523 | Substation-Adjacent | 230 kV | 300 MW | 3.7 yrs | 68.2 |
| TAP142146 | Substation-Adjacent | 115 kV | 100 MW | 3.7 yrs | 67.7 |
| UNKNOWN170157 | Substation-Adjacent | 115 kV | 100 MW | 3.7 yrs | 67.6 |
| TAP170158 | Substation-Adjacent | 115 kV | 100 MW | 3.7 yrs | 66.4 |
| TAP170160 | Substation-Adjacent | 230 kV | 300 MW | 3.7 yrs | 66.3 |
| TAP142140 | Substation-Adjacent | 115 kV | 100 MW | 3.7 yrs | 65.5 |
| TAP142154 | Substation-Adjacent | 230 kV | 300 MW | 3.7 yrs | 65.1 |
| YEMASSEE | Substation-Adjacent | 230 kV | 300 MW | 3.7 yrs | 65.0 |
| UNKNOWN121158 | Substation-Adjacent | 115 kV | 100 MW | 3.7 yrs | 64.6 |
| TAP170162 | Substation-Adjacent | 115 kV | 100 MW | 3.7 yrs | 64.0 |
| UNKNOWN121080 | Substation-Adjacent | 230 kV | 300 MW | 3.7 yrs | 63.5 |
| Greenfield (YEMASSEE - TAP170160) | Greenfield | 230 kV | 300 MW | 3.7 yrs | 63.4 |
| Greenfield (SANTEE COOPER - TAP167523) | Greenfield | 230 kV | 300 MW | 3.7 yrs | 63.4 |
| Greenfield (YEMASSEE - TAP170160) | Greenfield | 230 kV | 300 MW | 3.7 yrs | 63.2 |
| UNKNOWN121159 | Substation-Adjacent | 115 kV | 100 MW | 3.7 yrs | 62.8 |
| TAP142380 | Substation-Adjacent | 115 kV | 100 MW | 3.7 yrs | 62.7 |
| Greenfield (TAP142148 - TAP142380) | Greenfield | 115 kV | 100 MW | 3.7 yrs | 60.7 |
| EC Near Hardeeville | Greenfield | — | — | 3.7 yrs | 59.6 |
| Hardeeville | Brownfield | — | 16 MW | 3.7 yrs | 59.4 |
| EC Coal Jasper County | Greenfield | — | — | 3.7 yrs | 59.0 |
| EC Near Hardeeville | Greenfield | — | — | 3.7 yrs | 58.1 |
| EC Near Hardeeville | Greenfield | — | — | 3.7 yrs | 56.8 |
Jasper datacenter FAQ
- How many datacenter sites are in Jasper?
- 30 scored datacenter candidate sites, averaging 62.0/100 DC Readiness.
- Does Jasper offer datacenter tax incentives?
- Sales tax exemption on DC equipment; fee-in-lieu of property tax for $50M+ investments.
- What is the natural-hazard risk in Jasper?
- FEMA's National Risk Index rates Jasper as "Relatively High" (score 40).
- What are industrial electricity rates in Jasper?
- Average industrial electricity is 8.11¢/kWh and commercial is 11.87¢/kWh in Jasper.
Dataset updated . Screening estimates derived from public data sources.