Kershaw County, South Carolina · PJM

DC Readiness
56.0
Good / 100

TAP150587 is a substation-adjacent datacenter candidate site in Kershaw County, South Carolina, interconnecting through PJM. It screens at 56.0/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 4.3 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTAP150587
Substation distance0.0 mi
Substation voltage115 kV
Available capacity100 MW
LMP zonePJM_DUKE
Wholesale LMP$41.74/MWh
Utility commercial rate0.13¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth177
Avg queue wait4.3 yrs
Recent queue wait4.3 yrs
Completion rate14%
Withdrawal rate86%

Connectivity

Nearest IXPDartPoints Columbia, SC - CAE1
IXP distance46.9 mi
Fiber providers11
Fiber coverage58.7%
Nearest cloud providerGCP
Nearest cloud regionus-east1
Cloud region distance84.9 mi

Site characteristics

Parcel ownerPROGRESS ENERGY CAROLINAS INC
Land owner typeprivate
Buildability15.0/100
Land cover (NLCD)Woody Wetlands

Risk & environment

Flood zoneZone A (SFHA)
Water stress (WRI)0.80
Wetlands (NWI)Present
Critical habitatClear
Superfund nearbyClear
Hazard sub-score35/100
Construction cost index66.8 (avg 100)

Location context

Nearest datacenterDartPoints Columbia, SC - CAE1
DC distance46.9 mi
Nearest rail1.6 mi
Nearest gas pipeline0.4 mi
Nearest fiber route128.5 mi
County hazard (FEMA NRI)Relatively High (40)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.78¢/kWh
Industrial electricity7.39¢/kWh
Cooling degree days2,000
Heating degree days2,400
Land price / acre$3,888

Incentive detail: Sales tax exemption on DC equipment; fee-in-lieu of property tax for $50M+ investments.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
56
Speed to power15%
35
Fiber connectivity12%
66
Energy cost10%
82
Water risk8%
86
Natural hazard8%
35
Buildability7%
15
Labor market4%
50
DC cluster4%
50
Land / acreage3%
49
Construction cost3%
94
Gas pipeline2%
99
Tax incentive2%
100
Climate / cooling2%
25

Nearby comparable sites

Other scored datacenter candidate sites in Kershaw County, ranked by DC Readiness.

Sites near TAP150587
SiteTypeVoltageCapacityQueue waitScore
CAMDENSubstation-Adjacent230 kV300 MW4.3 yrs69.0
UNKNOWN120939Substation-Adjacent230 kV300 MW4.3 yrs66.9
UNKNOWN120940Substation-Adjacent230 kV300 MW4.3 yrs65.3
TAP154135Substation-Adjacent115 kV100 MW4.3 yrs64.5
Greenfield (BLYTHEWOOD - UNKNOWN120939)Greenfield230 kV300 MW4.3 yrs63.3
UNKNOWN120903Substation-Adjacent115 kV100 MW4.3 yrs62.6
UNKNOWN122762Substation-Adjacent115 kV100 MW4.3 yrs62.3
UNKNOWN120937Substation-Adjacent230 kV300 MW4.3 yrs61.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP150587, Kershaw County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.