Greenfield (DAVIDSON - CUMBERLAND 500KV)

Greenfield

Cheatham County, Tennessee · SERC

DC Readiness
71.3
Excellent / 100

Greenfield (DAVIDSON - CUMBERLAND 500KV) is a greenfield datacenter candidate site in Cheatham County, Tennessee, interconnecting through SERC. It screens at 71.3/100 DC Readiness with a catalogued 1,000 MW of candidate capacity and a 3.7 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationDAVIDSON
Substation voltage500 kV
Available capacity1,000 MW
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionSERC
Queue depth1
Avg queue wait3.7 yrs
Recent queue wait3.5 yrs
Completion rate15%
Withdrawal rate85%

Connectivity

Nearest IXPLevel(3) Nashville (9th Ave)
IXP distance17.2 mi
Fiber providers5
Fiber coverage78.4%
Nearest cloud providerAWS
Nearest cloud regionus-east-2
Cloud region distance345.3 mi

Site characteristics

Site typeGreenfield
Parcel ownerTENNESSEE VALLEY AUTHORITY
Land owner typeprivate
Buildability50.0/100

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score62/100
Construction cost index87.6 (avg 100)

Location context

Nearest datacenterLevel(3) Nashville (9th Ave)
DC distance17.2 mi
Nearest rail3.1 mi
Nearest gas pipeline3.0 mi
Nearest fiber route127.9 mi
County hazard (FEMA NRI)Relatively High (38)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.65¢/kWh
Industrial electricity6.64¢/kWh
Cooling degree days1,600
Heating degree days3,600
Land price / acre$6,673

Incentive detail: Sales tax exemption on DC equipment for $250M+ investments; no state income tax on wages.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
72
Speed to power15%
67
Fiber connectivity12%
78
Energy cost10%
90
Water risk8%
90
Natural hazard8%
62
Buildability7%
50
Labor market4%
50
DC cluster4%
60
Land / acreage3%
44
Construction cost3%
77
Gas pipeline2%
90
Tax incentive2%
100
Climate / cooling2%
45

Nearby comparable sites

Other scored datacenter candidate sites in Cheatham County, ranked by DC Readiness.

Sites near Greenfield (DAVIDSON - CUMBERLAND 500KV)
SiteTypeVoltageCapacityQueue waitScore
DAVIDSONSubstation-Adjacent500 kV1,000 MW3.7 yrs78.2
Greenfield (DAVIDSON - JOHNSONVILLE)Greenfield500 kV1,000 MW3.7 yrs72.1
BEARWALLOWSubstation-Adjacent161 kV100 MW3.7 yrs71.9
ASHLAND CITYSubstation-Adjacent161 kV100 MW3.7 yrs71.8
Greenfield (MONTGOMERY - DAVIDSON)Greenfield500 kV1,000 MW3.7 yrs71.6
KINGSTON SPRINGSSubstation-Adjacent161 kV100 MW3.7 yrs71.5
TAP155279Substation-Adjacent161 kV100 MW3.7 yrs70.7
Greenfield (MONTGOMERY - DAVIDSON)Greenfield500 kV1,000 MW3.7 yrs70.4

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (DAVIDSON - CUMBERLAND 500KV), Cheatham County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.