Datacenter Sites in Haywood County, Tennessee
Haywood County has 21 scored datacenter candidate sites averaging 61.3/100 DC Readiness, with a catalogued aggregate of 8,200 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
21
Candidate sites
61.3/100
Avg DC Readiness
8,200 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Haywood County
Yessales_tax_exemption
Datacenter tax incentive
13.10¢/kWh
Commercial electricity
8.53¢/kWh
Industrial electricity
6
Fiber providers
Low
Water stress
$3,625
Land price / acre
1,600
Cooling degree days
3,600
Heating degree days
58°F
Mean annual temp
Incentive detail: Sales tax exemption on DC equipment for $250M+ investments; no state income tax on wages.
By site type
Top datacenter sites in Haywood County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| LAGOON CREEK | Substation-Adjacent | 500 kV | 1,000 MW | 3.7 yrs | 73.2 |
| Greenfield (BROWNSVILLE - TAP154774) | Greenfield | 500 kV | 1,000 MW | 3.7 yrs | 69.3 |
| Greenfield (BROWNSVILLE - TAP154774) | Greenfield | 500 kV | 1,000 MW | 3.7 yrs | 67.4 |
| BROWNSVILLE INDL.PK. | Substation-Adjacent | 161 kV | 100 MW | 3.7 yrs | 67.2 |
| TAP154792 | Substation-Adjacent | 161 kV | 100 MW | 3.7 yrs | 65.2 |
| UNKNOWN159911 | Substation-Adjacent | 161 kV | 100 MW | 3.7 yrs | 64.6 |
| UNKNOWN115427 | Substation-Adjacent | 161 kV | 100 MW | 3.7 yrs | 63.1 |
| Greenfield (SHELBY - LAGOON CREEK) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 62.2 |
| Greenfield (SHELBY - LAGOON CREEK) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 61.0 |
| TAP154790 | Substation-Adjacent | 161 kV | 100 MW | 3.7 yrs | 60.9 |
| UNKNOWN120789 | Substation-Adjacent | 161 kV | 100 MW | 3.7 yrs | 60.7 |
| Greenfield (BROWNSVILLE INDL.PK. - TAP1547) | Greenfield | 161 kV | 100 MW | 3.7 yrs | 60.6 |
| TAP154791 | Substation-Adjacent | 161 kV | 100 MW | 3.7 yrs | 60.6 |
| Greenfield (ALAMO - TAP154790) | Greenfield | 161 kV | 100 MW | 3.7 yrs | 60.4 |
| Greenfield (BROWNSVILLE - CORDOVA) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 59.9 |
| TAP154786 | Substation-Adjacent | 161 kV | 100 MW | 3.7 yrs | 59.8 |
| OZ Haywood | Greenfield | — | — | 3.7 yrs | 59.4 |
| Greenfield (BROWNSVILLE INDL.PK. - TAP1547) | Greenfield | 161 kV | 100 MW | 3.7 yrs | 59.0 |
| Greenfield (TAP154786 - TAP154818) | Greenfield | 161 kV | 100 MW | 3.7 yrs | 55.7 |
| Greenfield (WEAKLEY - LAGOON CREEK) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 55.3 |
| I-40 Advantage Industrial Park Site | Shovel-Ready | — | — | — | 42.8 |
Haywood County datacenter FAQ
- How many datacenter sites are in Haywood County?
- 21 scored datacenter candidate sites, averaging 61.3/100 DC Readiness.
- Does Haywood County offer datacenter tax incentives?
- Sales tax exemption on DC equipment for $250M+ investments; no state income tax on wages.
- What is the natural-hazard risk in Haywood County?
- FEMA's National Risk Index rates Haywood County as "Relatively High" (score 38).
- What are industrial electricity rates in Haywood County?
- Average industrial electricity is 8.53¢/kWh and commercial is 13.10¢/kWh in Haywood County.
Dataset updated . Screening estimates derived from public data sources.