Datacenter Sites in Winkler County, Texas
Winkler County has 26 scored datacenter candidate sites averaging 54.8/100 DC Readiness, with a catalogued aggregate of 2,400 MW. FEMA rates local natural-hazard risk as "Very High". The county has a datacenter tax incentive on record.
26
Candidate sites
54.8/100
Avg DC Readiness
2,400 MW
Catalogued capacity
theoretical aggregate
Very High
Hazard rating
Site-selection context for Winkler County
Yessales_tax_exemption
Datacenter tax incentive
9.21¢/kWh
Commercial electricity
4.87¢/kWh
Industrial electricity
1
Fiber providers
Medium-High
Water stress
$1,520
Land price / acre
2,600
Cooling degree days
1,800
Heating degree days
65°F
Mean annual temp
Incentive detail: Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.
By site type
Top datacenter sites in Winkler County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| MIDWAY | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 61.7 |
| CHEYENE | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 61.6 |
| TAP310909 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 60.9 |
| UNKNOWN306393 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 60.2 |
| TAP310660 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 59.7 |
| UNOCAL DOLLARHIDE | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 59.7 |
| JAL | Substation-Adjacent | 115 kV | 100 MW | 3.4 yrs | 59.5 |
| UNKNOWN305094 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 59.1 |
| WHITTEN | Substation-Adjacent | 115 kV | 100 MW | 3.4 yrs | 59.1 |
| DOLLARHIDE | Substation-Adjacent | 115 kV | 100 MW | 3.4 yrs | 59.0 |
| Greenfield (TAP310660 - TAP310909) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 55.4 |
| Greenfield (PERMIAN BASIN SWITCHING STATIO) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 55.0 |
| Greenfield (MIDWAY - PERMIAN BASIN SWITCHI) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 54.7 |
| Greenfield (TAP315848 - MIDWAY) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 54.4 |
| Greenfield (WHITTEN - WARD) | Greenfield | 115 kV | 100 MW | 3.4 yrs | 53.9 |
| Greenfield (PERMIAN BASIN SWITCHING STATIO) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 53.7 |
| Greenfield (TAP311753 - PERMIAN BASIN SWIT) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 53.6 |
| Greenfield (TAP310568 - PERMIAN BASIN SWIT) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 53.2 |
| Greenfield (TAP311753 - PERMIAN BASIN SWIT) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 52.8 |
| Greenfield (TAP311753 - WICKETT) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 52.4 |
| Greenfield (UNKNOWN305094 - UNOCAL DOLLARH) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 51.8 |
| Greenfield (None - TAP310660) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 48.0 |
| Greenfield (TAP318008 - TAP311753) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 48.0 |
| Greenfield (TEAGUE - JAL) | Greenfield | 115 kV | 100 MW | 3.4 yrs | 47.1 |
| Mine Site | Former Mine | — | — | — | 45.0 |
Winkler County datacenter FAQ
- How many datacenter sites are in Winkler County?
- 26 scored datacenter candidate sites, averaging 54.8/100 DC Readiness.
- Does Winkler County offer datacenter tax incentives?
- Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.
- What is the natural-hazard risk in Winkler County?
- FEMA's National Risk Index rates Winkler County as "Very High" (score 55).
- What are industrial electricity rates in Winkler County?
- Average industrial electricity is 4.87¢/kWh and commercial is 9.21¢/kWh in Winkler County.
Dataset updated . Screening estimates derived from public data sources.