Datacenter Sites in Yoakum County, Texas
Yoakum County has 41 scored datacenter candidate sites averaging 57.7/100 DC Readiness, with a catalogued aggregate of 7,300 MW. FEMA rates local natural-hazard risk as "Very High". The county has a datacenter tax incentive on record.
41
Candidate sites
57.7/100
Avg DC Readiness
7,300 MW
Catalogued capacity
theoretical aggregate
Very High
Hazard rating
Site-selection context for Yoakum County
Yessales_tax_exemption
Datacenter tax incentive
7.92¢/kWh
Commercial electricity
6.86¢/kWh
Industrial electricity
6
Fiber providers
Medium-High
Water stress
$1,606
Land price / acre
2,600
Cooling degree days
1,800
Heating degree days
65°F
Mean annual temp
Incentive detail: Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.
By site type
Top datacenter sites in Yoakum County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| TAP302515 | Substation-Adjacent | 230 kV | 300 MW | 3.4 yrs | 65.9 |
| UNKNOWN302167 | Substation-Adjacent | 230 kV | 300 MW | 3.4 yrs | 65.0 |
| WASSON SWITCHING | Substation-Adjacent | 230 kV | 300 MW | 3.4 yrs | 64.6 |
| DENVER CITY | Substation-Adjacent | 230 kV | 300 MW | 3.4 yrs | 64.6 |
| TAP308106 | Substation-Adjacent | 230 kV | 300 MW | 3.4 yrs | 62.9 |
| LEA CO. WAITS | Substation-Adjacent | 115 kV | 100 MW | 3.4 yrs | 61.9 |
| UNKNOWN318032 | Substation-Adjacent | 115 kV | 100 MW | 3.4 yrs | 61.8 |
| SAN ANDRES | Substation-Adjacent | 115 kV | 100 MW | 3.4 yrs | 61.6 |
| SHELL C3 | Substation-Adjacent | 115 kV | 100 MW | 3.4 yrs | 61.4 |
| CORTEZ | Substation-Adjacent | 115 kV | 100 MW | 3.4 yrs | 61.4 |
| UNKNOWN309885 | Substation-Adjacent | 115 kV | 100 MW | 3.4 yrs | 60.4 |
| TAP305155 | Substation-Adjacent | 115 kV | 100 MW | 3.4 yrs | 60.0 |
| TAP318055 | Substation-Adjacent | 115 kV | 100 MW | 3.4 yrs | 59.8 |
| SHELL CO2 | Substation-Adjacent | 115 kV | 100 MW | 3.4 yrs | 59.7 |
| ARCO BP-WILLARD | Substation-Adjacent | 115 kV | 100 MW | 3.4 yrs | 59.6 |
| TAP302530 | Substation-Adjacent | 115 kV | 100 MW | 3.4 yrs | 59.4 |
| Greenfield (WASSON SWITCHING - TAP302515) | Greenfield | 230 kV | 300 MW | 3.4 yrs | 59.3 |
| Greenfield (UNKNOWN301096 - UNKNOWN302167) | Greenfield | 230 kV | 300 MW | 3.4 yrs | 59.2 |
| Greenfield (UNKNOWN302167 - UNKNOWN307246) | Greenfield | 230 kV | 300 MW | 3.4 yrs | 59.0 |
| HIGG | Substation-Adjacent | 115 kV | 100 MW | 3.4 yrs | 58.9 |
| Greenfield (UNKNOWN307714 - UNKNOWN302167) | Greenfield | 230 kV | 300 MW | 3.4 yrs | 58.3 |
| EL PASO | Substation-Adjacent | 115 kV | 100 MW | 3.4 yrs | 58.0 |
| Greenfield (UNKNOWN307714 - UNKNOWN302167) | Greenfield | 230 kV | 300 MW | 3.4 yrs | 57.9 |
| Greenfield (UNKNOWN302167 - TAP308106) | Greenfield | 230 kV | 300 MW | 3.4 yrs | 57.8 |
| Greenfield (UNKNOWN301096 - UNKNOWN302167) | Greenfield | 230 kV | 300 MW | 3.4 yrs | 57.7 |
Yoakum County datacenter FAQ
- How many datacenter sites are in Yoakum County?
- 41 scored datacenter candidate sites, averaging 57.7/100 DC Readiness.
- Does Yoakum County offer datacenter tax incentives?
- Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.
- What is the natural-hazard risk in Yoakum County?
- FEMA's National Risk Index rates Yoakum County as "Very High" (score 55).
- What are industrial electricity rates in Yoakum County?
- Average industrial electricity is 6.86¢/kWh and commercial is 7.92¢/kWh in Yoakum County.
Dataset updated . Screening estimates derived from public data sources.