Greenfield (FIREHOLE - LITTLE MOUNTAIN)

Greenfield

Daggett County, Utah · WECC

DC Readiness
57.5
Good / 100

Greenfield (FIREHOLE - LITTLE MOUNTAIN) is a greenfield datacenter candidate site in Daggett County, Utah, interconnecting through WECC. It screens at 57.5/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 1.7 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationFIREHOLE
Substation voltage230 kV
Available capacity300 MW
Utility commercial rate0.09¢/kWh

Speed to power

ISO / RTO regionWECC
Queue depth74
Avg queue wait1.7 yrs
Recent queue wait1.0 yrs
Completion rate17%
Withdrawal rate84%

Connectivity

Nearest IXPSTRATA Vernal Data Center
IXP distance52.0 mi
Fiber providers2
Fiber coverage43.1%
Nearest cloud providerGCP
Nearest cloud regionus-west3
Cloud region distance138.8 mi

Site characteristics

Site typeGreenfield
Parcel ownerPACIFICORP
Land owner typeprivate
Buildability70.0/100
Land cover (NLCD)Shrub/Scrub

Risk & environment

Flood zoneZone X
Water stress (WRI)3.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score85/100
Construction cost index86.7 (avg 100)

Location context

Nearest datacenterStrata Networks
DC distance52.0 mi
Nearest rail2.4 mi
Nearest gas pipeline1.2 mi
Nearest fiber route102.1 mi
County hazard (FEMA NRI)Relatively Low (15)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity9.00¢/kWh
Industrial electricity9.13¢/kWh
Cooling degree days1,000
Heating degree days5,500
Land price / acre$3,609

Incentive detail: Enterprise Zone tax credits; Economic Development Tax Increment Financing (EDTIF).

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
50
Speed to power15%
34
Fiber connectivity12%
47
Energy cost10%
96
Water risk8%
29
Natural hazard8%
85
Buildability7%
70
Labor market4%
50
DC cluster4%
45
Land / acreage3%
50
Construction cost3%
78
Gas pipeline2%
96
Tax incentive2%
100
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in Daggett County, ranked by DC Readiness.

Sites near Greenfield (FIREHOLE - LITTLE MOUNTAIN)
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN205944Substation-Adjacent138 kV100 MW1.7 yrs65.1
FLAMING GORGESubstation-Adjacent230 kV300 MW1.7 yrs64.8
TAP205943Substation-Adjacent138 kV100 MW1.7 yrs63.7
UNKNOWN202533Substation-Adjacent138 kV100 MW1.7 yrs63.4
LITTLE MOUNTAINSubstation-Adjacent230 kV300 MW1.7 yrs59.8
Greenfield (VERNAL - FLAMING GORGE)Greenfield138 kV100 MW1.7 yrs59.8
Greenfield (LITTLE MOUNTAIN - FLAMING GORG)Greenfield230 kV300 MW1.7 yrs58.9
Greenfield (FIREHOLE - LITTLE MOUNTAIN)Greenfield230 kV300 MW1.7 yrs57.3

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (FIREHOLE - LITTLE MOUNTAIN), Daggett County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.