Datacenter Sites in Juab County, Utah
Juab County has 42 scored datacenter candidate sites averaging 50.5/100 DC Readiness, with a catalogued aggregate of 10,500 MW. FEMA rates local natural-hazard risk as "Relatively Low". The county has a datacenter tax incentive on record.
42
Candidate sites
50.5/100
Avg DC Readiness
10,500 MW
Catalogued capacity
theoretical aggregate
Relatively Low
Hazard rating
Site-selection context for Juab County
Yessales_tax_exemption
Datacenter tax incentive
9.45¢/kWh
Commercial electricity
7.73¢/kWh
Industrial electricity
2
Fiber providers
High
Water stress
$2,646
Land price / acre
1,000
Cooling degree days
5,500
Heating degree days
49°F
Mean annual temp
Incentive detail: Enterprise Zone tax credits; Economic Development Tax Increment Financing (EDTIF).
By site type
Top datacenter sites in Juab County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| INTERMOUNTAIN | Substation-Adjacent | 500 kV | 1,000 MW | 5.7 yrs | 67.3 |
| UNKNOWN208830 | Substation-Adjacent | 128 kV | 100 MW | 1.7 yrs | 64.0 |
| Greenfield (INTERMOUNTAIN - MONA) | Greenfield | 345 kV | 600 MW | 1.7 yrs | 63.1 |
| UNKNOWN208850 | Substation-Adjacent | 128 kV | 100 MW | 1.7 yrs | 62.4 |
| TAP208829 | Substation-Adjacent | 128 kV | 100 MW | 1.7 yrs | 62.1 |
| Greenfield (INTERMOUNTAIN - ADELANTO) | Greenfield | 500 kV | 1,000 MW | 5.7 yrs | 61.9 |
| UNKNOWN208841 | Substation-Adjacent | 128 kV | 100 MW | 1.7 yrs | 61.2 |
| Greenfield (INTERMOUNTAIN - MONA) | Greenfield | 345 kV | 600 MW | 1.7 yrs | 60.8 |
| Greenfield (INTERMOUNTAIN - ADELANTO) | Greenfield | 500 kV | 1,000 MW | 5.7 yrs | 60.7 |
| Greenfield (INTERMOUNTAIN - ADELANTO) | Greenfield | 500 kV | 1,000 MW | 5.7 yrs | 60.0 |
| Greenfield (INTERMOUNTAIN - ADELANTO) | Greenfield | 500 kV | 1,000 MW | 5.7 yrs | 59.7 |
| Greenfield (MILDFORD WIND - INTERMOUNTAIN) | Greenfield | 345 kV | 600 MW | 1.7 yrs | 59.3 |
| Greenfield (MILDFORD WIND - INTERMOUNTAIN) | Greenfield | 345 kV | 600 MW | 1.7 yrs | 58.9 |
| Greenfield (MILDFORD WIND - INTERMOUNTAIN) | Greenfield | 345 kV | 600 MW | 1.7 yrs | 58.8 |
| Greenfield (TAP208829 - UNKNOWN208830) | Greenfield | 128 kV | 100 MW | 1.7 yrs | 57.5 |
| Greenfield (TAP208829 - UNKNOWN208830) | Greenfield | 128 kV | 100 MW | 1.7 yrs | 56.6 |
| Greenfield (TAP208827 - TAP208840) | Greenfield | 128 kV | 100 MW | 1.7 yrs | 56.6 |
| Greenfield (INTERMOUNTAIN - MONA) | Greenfield | 345 kV | 600 MW | 1.7 yrs | 56.6 |
| Greenfield (MILDFORD WIND - INTERMOUNTAIN) | Greenfield | 345 kV | 600 MW | 1.7 yrs | 55.1 |
| Greenfield (PAVANT - TAP208827) | Greenfield | 128 kV | 100 MW | 1.7 yrs | 55.0 |
| Greenfield (PAVANT - TAP208827) | Greenfield | 128 kV | 100 MW | 1.7 yrs | 54.9 |
| Greenfield (INTERMOUNTAIN - GONDER) | Greenfield | 230 kV | 300 MW | 5.8 yrs | 54.6 |
| Greenfield (PAVANT - TAP208827) | Greenfield | 128 kV | 100 MW | 1.7 yrs | 48.1 |
| CUP, BONNEVILLE UNIT | Federal Excess | — | — | — | 41.4 |
| CUP, BONNEVILLE UNIT | Federal Excess | — | — | — | 41.3 |
Juab County datacenter FAQ
- How many datacenter sites are in Juab County?
- 42 scored datacenter candidate sites, averaging 50.5/100 DC Readiness.
- Does Juab County offer datacenter tax incentives?
- Enterprise Zone tax credits; Economic Development Tax Increment Financing (EDTIF).
- What is the natural-hazard risk in Juab County?
- FEMA's National Risk Index rates Juab County as "Relatively Low" (score 15).
- What are industrial electricity rates in Juab County?
- Average industrial electricity is 7.73¢/kWh and commercial is 9.45¢/kWh in Juab County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Juab County, Utah. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.