Kane County, Utah · WECC

DC Readiness
58.4
Good / 100

POWELL is a substation-adjacent datacenter candidate site in Kane County, Utah, interconnecting through WECC. It screens at 58.4/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 5.7 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationPOWELL
Substation distance0.0 mi
Substation voltage138 kV
Available capacity100 MW
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionWECC
Queue depth68
Avg queue wait5.7 yrs
Recent queue wait5.7 yrs
Completion rate10%
Withdrawal rate90%

Connectivity

Nearest IXPTonaquint Data Center - Saint George
IXP distance118.2 mi
Fiber providers2
Fiber coverage54.2%
Nearest cloud providerGCP
Nearest cloud regionus-west4
Cloud region distance209.6 mi

Site characteristics

Parcel ownerGARKANE ENERGY COOP, INC
Land owner typeprivate
Buildability90.0/100
Land cover (NLCD)Developed, Open Space

Risk & environment

Flood zoneZone X
Water stress (WRI)3.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteLAKE POWELL FORD INC
Hazard sub-score75/100
Construction cost index56.8 (avg 100)

Location context

Nearest datacenterLumen
DC distance114.7 mi
Nearest rail4.8 mi
Nearest gas pipeline49.1 mi
Nearest fiber route172.2 mi
County hazard (FEMA NRI)Relatively Low (15)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.55¢/kWh
Industrial electricity6.95¢/kWh
Cooling degree days1,000
Heating degree days5,500
Land price / acre$4,475

Incentive detail: Enterprise Zone tax credits; Economic Development Tax Increment Financing (EDTIF).

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
58
Speed to power15%
30
Fiber connectivity12%
60
Energy cost10%
90
Water risk8%
32
Natural hazard8%
75
Buildability7%
90
Labor market4%
50
DC cluster4%
20
Land / acreage3%
63
Construction cost3%
100
Gas pipeline2%
0
Tax incentive2%
100
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in Kane County, ranked by DC Readiness.

Sites near POWELL
SiteTypeVoltageCapacityQueue waitScore
NAVAJOSubstation-Adjacent500 kV1,000 MW5.7 yrs71.1
UNKNOWN202288Substation-Adjacent230 kV300 MW1.7 yrs64.8
GLEN CANYONSubstation-Adjacent345 kV600 MW5.7 yrs63.9
Greenfield (NAVAJO - DUGAS)Greenfield500 kV1,000 MW5.7 yrs62.3
Greenfield (NAVAJO - CRYSTAL)Greenfield500 kV1,000 MW5.7 yrs61.7
HATCH DISTRIBUTIONSubstation-Adjacent138 kV100 MW1.7 yrs61.6
Greenfield (NAVAJO - CRYSTAL)Greenfield500 kV1,000 MW5.7 yrs61.4
UNKNOWN201828Substation-Adjacent230 kV300 MW1.7 yrs61.4

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for POWELL, Kane County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.