Greenfield (CLOVERDALE 765KV - JOSHUA FALL)
GreenfieldBotetourt, Virginia · PJM
Greenfield (CLOVERDALE 765KV - JOSHUA FALL) is a greenfield datacenter candidate site in Botetourt, Virginia, interconnecting through PJM. It screens at 68.4/100 DC Readiness with a catalogued 1,000 MW of candidate capacity and a 3.0 yrs average interconnection-queue wait.
Power & interconnection
Speed to power
Connectivity
Site characteristics
Risk & environment
Location context
Incentive detail: Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.
Full DC Readiness breakdown
All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.
Nearby comparable sites
Other scored datacenter candidate sites in Botetourt, ranked by DC Readiness.
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| CLOVERDALE EAST | Substation-Adjacent | 500 kV | 1,000 MW | 3.0 yrs | 75.6 |
| Greenfield (LEXINGTON - CLOVERDALE EAST) | Greenfield | 500 kV | 1,000 MW | 3.0 yrs | 68.7 |
| Greenfield (LEXINGTON - CLOVERDALE EAST) | Greenfield | 500 kV | 1,000 MW | 3.0 yrs | 67.1 |
| UNKNOWN121374 | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 65.6 |
| Greenfield (LEXINGTON - CLOVERDALE EAST) | Greenfield | 500 kV | 1,000 MW | 3.0 yrs | 65.5 |
| Greenfield (LOWMOOR - LEXINGTON) | Greenfield | 230 kV | 300 MW | 3.0 yrs | 62.7 |
| Greenfield (LOWMOOR - LEXINGTON) | Greenfield | 230 kV | 300 MW | 3.0 yrs | 59.2 |
| MTI GROENDYK, INC. (RUBBER PRODUCT MANUFACTURING FOR MECHANICAL USE) | Manufacturing | — | — | — | 50.6 |
Dataset updated . Screening estimates derived from public data sources.
Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Greenfield (CLOVERDALE 765KV - JOSHUA FALL), Botetourt. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.