Greenfield (WAKE - CARSON)

Greenfield

Greensville County, Virginia · PJM

DC Readiness
61.3
Good / 100

Greenfield (WAKE - CARSON) is a greenfield datacenter candidate site in Greensville County, Virginia, interconnecting through PJM. It screens at 61.3/100 DC Readiness with a catalogued 1,000 MW of candidate capacity and a 3.1 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationWAKE
Substation voltage500 kV
Available capacity1,000 MW
LMP zonePJM_DOM
Wholesale LMP$43.92/MWh
Utility commercial rate0.05¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth864
Avg queue wait3.1 yrs
Recent queue wait3.6 yrs
Completion rate20%
Withdrawal rate80%

Connectivity

Nearest IXPLevel(3) Raleigh
IXP distance68.1 mi
Fiber providers3
Fiber coverage66.7%
Nearest cloud providerAzure
Nearest cloud regioneastus2
Cloud region distance35.7 mi

Site characteristics

Site typeGreenfield
Parcel ownerVIRGINIA ELECTRIC & POWER CO
Land owner typeprivate
Buildability40.0/100
Land cover (NLCD)Evergreen Forest

Risk & environment

Flood zoneZone X
Water stress (WRI)0.60
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score70/100
Construction cost index73.5 (avg 100)

Location context

Nearest datacenterMicrosoft Boydton Data Center
DC distance35.3 mi
Nearest rail8.6 mi
Nearest gas pipeline6.8 mi
Nearest fiber route74.5 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity4.93¢/kWh
Industrial electricity5.27¢/kWh
Cooling degree days1,300
Heating degree days4,000
Land price / acre$2,861

Incentive detail: Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
72
Speed to power15%
44
Fiber connectivity12%
23
Energy cost10%
95
Water risk8%
85
Natural hazard8%
70
Buildability7%
40
Labor market4%
50
DC cluster4%
50
Land / acreage3%
46
Construction cost3%
89
Gas pipeline2%
78
Tax incentive2%
100
Climate / cooling2%
60

Nearby comparable sites

Other scored datacenter candidate sites in Greensville County, ranked by DC Readiness.

Sites near Greenfield (WAKE - CARSON)
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN111421Substation-Adjacent230 kV300 MW3.1 yrs70.4
Greenfield (WAKE - CARSON)Greenfield500 kV1,000 MW3.1 yrs68.4
TAP148238Substation-Adjacent115 kV100 MW3.1 yrs65.8
TAP148237Substation-Adjacent115 kV100 MW3.1 yrs65.7
TAP148227Substation-Adjacent115 kV100 MW3.1 yrs64.3
TREGOSubstation-Adjacent115 kV100 MW3.1 yrs64.0
Greenfield (UNKNOWN111421 - TAP148228)Greenfield230 kV300 MW3.1 yrs63.6
TAP148229Substation-Adjacent115 kV100 MW3.1 yrs63.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (WAKE - CARSON), Greensville County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.