Hanover, Virginia · PJM

DC Readiness
69.2
Good / 100

HANOVER is a substation-adjacent datacenter candidate site in Hanover, Virginia, interconnecting through PJM. It screens at 69.2/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 3.1 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationHANOVER
Substation distance0.0 mi
Substation voltage230 kV
Available capacity300 MW
LMP zonePJM_DOM
Wholesale LMP$43.92/MWh
Utility commercial rate0.08¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth864
Avg queue wait3.1 yrs
Recent queue wait3.6 yrs
Completion rate20%
Withdrawal rate80%

Connectivity

Nearest IXPPixel Factory Data Center
IXP distance4.1 mi
Fiber providers6
Fiber coverage48.8%
Nearest cloud providerAWS
Nearest cloud regionus-east-1
Cloud region distance89.2 mi

Site characteristics

Parcel ownerVIRGINIA ELECTRIC & POWER CO
Land owner typeprivate
Buildability95.0/100
Land cover (NLCD)Developed, Medium Intensity

Risk & environment

Flood zoneZone X
Water stress (WRI)0.60
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteWALMART SUPERCENTER 2795
Hazard sub-score60/100
Construction cost index92.1 (avg 100)

Location context

Nearest datacenterPixel Factory Data Center
DC distance4.1 mi
Nearest rail1.1 mi
Nearest gas pipeline4.9 mi
Nearest fiber route48.5 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity7.92¢/kWh
Industrial electricity6.15¢/kWh
Cooling degree days1,300
Heating degree days4,000
Land price / acre$6,759

Incentive detail: Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
78
Speed to power15%
44
Fiber connectivity12%
51
Energy cost10%
83
Water risk8%
88
Natural hazard8%
60
Buildability7%
95
Labor market4%
50
DC cluster4%
90
Land / acreage3%
46
Construction cost3%
73
Gas pipeline2%
84
Tax incentive2%
100
Climate / cooling2%
60

Nearby comparable sites

Other scored datacenter candidate sites in Hanover, ranked by DC Readiness.

Sites near HANOVER
SiteTypeVoltageCapacityQueue waitScore
ELMONTSubstation-Adjacent500 kV1,000 MW3.1 yrs79.3
SHORT PUMPSubstation-Adjacent230 kV300 MW3.0 yrs74.6
FOUR RIVERSSubstation-Adjacent230 kV300 MW3.1 yrs73.7
MOUNTAIN ROADSubstation-Adjacent230 kV300 MW3.1 yrs73.5
BEAR ISLANDSubstation-Adjacent230 kV300 MW3.1 yrs72.6
Greenfield (ELMONT - CUNNINGHAM)Greenfield500 kV1,000 MW3.0 yrs71.2
PEARSONSSubstation-Adjacent230 kV300 MW3.1 yrs71.1
SHORT PUMPSubstation-Adjacent230 kV300 MW3.1 yrs69.6

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen