Transalta Centralia Generation

Brownfield

Thurston County, Washington · WECC

DC Readiness
68.2
Good / 100

Transalta Centralia Generation is a brownfield datacenter candidate site in Thurston County, Washington, interconnecting through WECC. It screens at 68.2/100 DC Readiness with a catalogued 1,052 MW of candidate capacity.

Power & interconnection

Substation distance0.1 mi
Available capacity1,052 MW
Utility commercial rate0.08¢/kWh

Speed to power

ISO / RTO regionWECC
Queue depth74

Connectivity

Nearest IXPScaleMatrix Seattle Data Center US-West 02
IXP distance38.9 mi
Fiber providers10
Nearest cloud providerAWS
Nearest cloud regionus-west-2
Cloud region distance86.1 mi

Site characteristics

Site typeBrownfield
Land owner typeprivate
Buildability100.0/100
Land cover (NLCD)Developed, High Intensity
Former usecoal
Existing capacity1,052 MW
Retirement date2020-12-01

Risk & environment

Flood zoneZone X
Water stress (WRI)1.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteTRANSALTA CENTRALIA GENERATION LLC
Hazard sub-score62/100
Construction cost index102.7 (avg 100)

Location context

Nearest datacenterWave Broadband Tahoma Terra Facility
DC distance17.0 mi
Nearest rail0.1 mi
Nearest gas pipeline2.1 mi
County hazard (FEMA NRI)Relatively Moderate (28)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity8.42¢/kWh
Industrial electricity6.52¢/kWh
Cooling degree days300
Heating degree days5,000
Land price / acre$17,717

Incentive detail: Sales tax exemption on DC equipment and construction for eligible facilities; no state income tax.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
75
Speed to power15%
55
Fiber connectivity12%
30
Energy cost10%
100
Water risk8%
64
Natural hazard8%
62
Buildability7%
100
Labor market4%
50
DC cluster4%
70
Land / acreage3%
57
Construction cost3%
64
Gas pipeline2%
93
Tax incentive2%
100
Climate / cooling2%
100

Nearby comparable sites

Other scored datacenter candidate sites in Thurston County, ranked by DC Readiness.

Sites near Transalta Centralia Generation
SiteTypeVoltageCapacityQueue waitScore
TRANSALTA CENTRALIA GENERATIONSubstation-Adjacent500 kV1,000 MW1.7 yrs76.1
PAULSubstation-Adjacent500 kV1,000 MW1.7 yrs73.6
OLYMPIASubstation-Adjacent500 kV1,000 MW1.7 yrs71.9
YELM PPSubstation-Adjacent230 kV300 MW1.7 yrs69.5
CHEHALISSubstation-Adjacent230 kV300 MW1.7 yrs69.1
MAY STREETSubstation-Adjacent230 kV300 MW1.7 yrs68.4
NAPAVINESubstation-Adjacent500 kV1,000 MW1.7 yrs67.7
TAP200417Substation-Adjacent230 kV300 MW1.7 yrs67.5

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Transalta Centralia Generation, Thurston County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.