Mingo County, West Virginia · PJM

DC Readiness
63.3
Good / 100

SPRIGG is a substation-adjacent datacenter candidate site in Mingo County, West Virginia, interconnecting through PJM. It screens at 63.3/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.6 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationSPRIGG
Substation distance0.0 mi
Substation voltage138 kV
Available capacity100 MW
LMP zonePJM_DUKE
Wholesale LMP$41.74/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth221
Avg queue wait3.6 yrs
Recent queue wait4.7 yrs
Completion rate7%
Withdrawal rate93%

Connectivity

Nearest IXPEast Kentucky Network Data Center
IXP distance26.7 mi
Fiber providers2
Fiber coverage13.0%
Nearest cloud providerAzure
Nearest cloud regioneastus
Cloud region distance132.0 mi

Site characteristics

Parcel ownerAPPALACHIAN POWER CO
Land owner typeprivate
Buildability60.0/100

Risk & environment

Flood zoneZone X
Water stress (WRI)0.40
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score78/100
Construction cost index66.1 (avg 100)

Location context

Nearest datacenterEast Kentucky Network Datacenter
DC distance26.6 mi
Nearest rail1.2 mi
Nearest gas pipeline3.6 mi
Nearest fiber route190.5 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveNo
Commercial electricity12.35¢/kWh
Industrial electricity8.76¢/kWh
Cooling degree days800
Heating degree days5,000
Land price / acre$1,361

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
58
Speed to power15%
36
Fiber connectivity12%
55
Energy cost10%
93
Water risk8%
92
Natural hazard8%
78
Buildability7%
60
Labor market4%
50
DC cluster4%
65
Land / acreage3%
54
Construction cost3%
95
Gas pipeline2%
89
Tax incentive2%
0
Climate / cooling2%
85

Nearby comparable sites

Other scored datacenter candidate sites in Mingo County, ranked by DC Readiness.

Sites near SPRIGG
SiteTypeVoltageCapacityQueue waitScore
CINDERSubstation-Adjacent138 kV100 MW3.6 yrs61.2
EC Coal Mingo CountyGreenfield3.0 yrs60.3
TAP155907Substation-Adjacent138 kV100 MW3.6 yrs59.5
HATFIELD (KP)Substation-Adjacent138 kV100 MW3.6 yrs58.8
OZ MingoGreenfield3.0 yrs58.2
EC Coal Mingo CountyGreenfield3.0 yrs58.1
EC Coal Mingo CountyGreenfield3.0 yrs57.4
EC Coal Mingo CountyGreenfield3.0 yrs56.9

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.