Datacenter Sites in Dunn County, Wisconsin
Dunn County has 28 scored datacenter candidate sites averaging 56.2/100 DC Readiness, with a catalogued aggregate of 3,871 MW. FEMA rates local natural-hazard risk as "Relatively Low". The county has a datacenter tax incentive on record.
28
Candidate sites
56.2/100
Avg DC Readiness
3,871 MW
Catalogued capacity
theoretical aggregate
Relatively Low
Hazard rating
Site-selection context for Dunn County
Yessales_tax_exemption
Datacenter tax incentive
11.55¢/kWh
Commercial electricity
8.44¢/kWh
Industrial electricity
11
Fiber providers
Low
Water stress
$4,904
Land price / acre
600
Cooling degree days
7,200
Heating degree days
44°F
Mean annual temp
Incentive detail: Enterprise Zone tax credits; TIF available for DC construction in eligible areas.
By site type
Top datacenter sites in Dunn County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| Greenfield (UNKNOWN129869 - KING PLANT) | Greenfield | 345 kV | 600 MW | 1.4 yrs | 69.7 |
| ELK MOUND | Substation-Adjacent | 161 kV | 100 MW | 1.4 yrs | 69.5 |
| UNKNOWN163358 | Substation-Adjacent | 161 kV | 100 MW | 1.4 yrs | 69.2 |
| Greenfield (UNKNOWN129869 - KING PLANT) | Greenfield | 345 kV | 600 MW | 1.4 yrs | 68.7 |
| Greenfield (UNKNOWN129869 - KING PLANT) | Greenfield | 345 kV | 600 MW | 1.4 yrs | 67.8 |
| Greenfield (UNKNOWN131984 - UNKNOWN132591) | Greenfield | 115 kV | 100 MW | 1.4 yrs | 65.1 |
| Greenfield (UNKNOWN131981 - UNKNOWN163358) | Greenfield | 161 kV | 100 MW | 1.4 yrs | 65.0 |
| Greenfield (UNKNOWN129869 - KING PLANT) | Greenfield | 345 kV | 600 MW | 1.4 yrs | 64.4 |
| Greenfield (UNKNOWN131981 - UNKNOWN163358) | Greenfield | 161 kV | 100 MW | 1.4 yrs | 64.2 |
| Greenfield (UNKNOWN131984 - UNKNOWN132591) | Greenfield | 115 kV | 100 MW | 1.4 yrs | 63.5 |
| Greenfield (ELK MOUND - BARRON) | Greenfield | 161 kV | 100 MW | 1.4 yrs | 62.9 |
| Elk Mound | Brownfield | — | 71 MW | 1.4 yrs | 62.6 |
| Greenfield (ELK MOUND - BARRON) | Greenfield | 161 kV | 100 MW | 1.4 yrs | 62.5 |
| Greenfield (UNKNOWN131984 - UNKNOWN132591) | Greenfield | 115 kV | 100 MW | 1.4 yrs | 62.4 |
| Greenfield (UNKNOWN131984 - UNKNOWN132591) | Greenfield | 115 kV | 100 MW | 1.4 yrs | 62.1 |
| Greenfield (WHEATON - UNKNOWN163358) | Greenfield | 161 kV | 100 MW | 1.4 yrs | 60.0 |
| Greenfield (UNKNOWN131981 - UNKNOWN163358) | Greenfield | 161 kV | 100 MW | 1.4 yrs | 58.7 |
| Greenfield (UNKNOWN131984 - UNKNOWN132591) | Greenfield | 115 kV | 100 MW | 1.4 yrs | 58.7 |
| Greenfield (ELK MOUND - BARRON) | Greenfield | 161 kV | 100 MW | 1.4 yrs | 56.7 |
| Mine Site | Former Mine | — | — | — | 44.0 |
| Mine Site | Former Mine | — | — | — | 42.5 |
| Menomonie Industrial Park | Shovel-Ready | — | — | — | 39.2 |
| Menomonie Industrial Park | Shovel-Ready | — | — | — | 39.2 |
| Menomonie Industrial Park | Shovel-Ready | — | — | — | 39.2 |
| Menomonie Industrial Park | Shovel-Ready | — | — | — | 39.1 |
Dunn County datacenter FAQ
- How many datacenter sites are in Dunn County?
- 28 scored datacenter candidate sites, averaging 56.2/100 DC Readiness.
- Does Dunn County offer datacenter tax incentives?
- Enterprise Zone tax credits; TIF available for DC construction in eligible areas.
- What is the natural-hazard risk in Dunn County?
- FEMA's National Risk Index rates Dunn County as "Relatively Low" (score 22).
- What are industrial electricity rates in Dunn County?
- Average industrial electricity is 8.44¢/kWh and commercial is 11.55¢/kWh in Dunn County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Dunn County, Wisconsin. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.