Greenfield (NORTHPOINT - TAP144262)

Greenfield

Portage County, Wisconsin · MISO

DC Readiness
62.6
Good / 100

Greenfield (NORTHPOINT - TAP144262) is a greenfield datacenter candidate site in Portage County, Wisconsin, interconnecting through MISO. It screens at 62.6/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 1.4 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationNORTHPOINT
Substation voltage115 kV
Available capacity100 MW
LMP zoneMISO_MINN
Wholesale LMP$34.82/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionMISO
Queue depth16
Avg queue wait1.4 yrs
Recent queue wait1.4 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXP901 Commerce Dr
IXP distance27.9 mi
Fiber providers7
Fiber coverage76.0%
Nearest cloud providerAzure
Nearest cloud regionnorthcentralus
Cloud region distance215.1 mi

Site characteristics

Site typeGreenfield
Parcel ownerAMERICAN TRANSMISSION CO
Land owner typeprivate
Buildability50.0/100

Risk & environment

Flood zoneZone X
Water stress (WRI)0.30
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score78/100
Construction cost index81.8 (avg 100)

Location context

Nearest datacenter901 Commerce Dr
DC distance27.9 mi
Nearest rail6.4 mi
Nearest gas pipeline0.6 mi
Nearest fiber route58.2 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.01¢/kWh
Industrial electricity8.14¢/kWh
Cooling degree days600
Heating degree days7,200
Land price / acre$4,888

Incentive detail: Enterprise Zone tax credits; TIF available for DC construction in eligible areas.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
28
Speed to power15%
57
Fiber connectivity12%
69
Energy cost10%
87
Water risk8%
94
Natural hazard8%
78
Buildability7%
50
Labor market4%
50
DC cluster4%
60
Land / acreage3%
47
Construction cost3%
82
Gas pipeline2%
98
Tax incentive2%
100
Climate / cooling2%
95

Nearby comparable sites

Other scored datacenter candidate sites in Portage County, ranked by DC Readiness.

Sites near Greenfield (NORTHPOINT - TAP144262)
SiteTypeVoltageCapacityQueue waitScore
ROCKY RUNSubstation-Adjacent345 kV600 MW1.4 yrs75.8
Greenfield (GARDNER PARK - ROCKY RUN)Greenfield345 kV600 MW1.4 yrs71.0
ARNOTTSubstation-Adjacent138 kV100 MW1.4 yrs70.2
Greenfield (WERNER WEST - ROCKY RUN)Greenfield345 kV600 MW1.4 yrs68.8
Greenfield (WERNER WEST - ROCKY RUN)Greenfield345 kV600 MW1.4 yrs68.4
Greenfield (WERNER WEST - ROCKY RUN)Greenfield345 kV600 MW1.4 yrs67.8
HARTMAN CREEKSubstation-Adjacent138 kV100 MW1.4 yrs66.7
PLOVERSubstation-Adjacent115 kV100 MW1.4 yrs66.4

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (NORTHPOINT - TAP144262), Portage County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.