EC Coal Vernon County

Greenfield

Vernon, Wisconsin · MISO

DC Readiness
61.2
Good / 100

EC Coal Vernon County is a greenfield datacenter candidate site in Vernon, Wisconsin, interconnecting through MISO. It screens at 61.2/100 DC Readiness and a 1.4 yrs average interconnection-queue wait.

Power & interconnection

LMP zoneMISO_ILLINOIS
Wholesale LMP$33.26/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionMISO
Queue depth41
Avg queue wait1.4 yrs
Recent queue wait1.4 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPSupraNet Communications Madison
IXP distance73.1 mi
Fiber providers4
Fiber coverage95.2%
Nearest cloud providerAzure
Nearest cloud regioncentralus
Cloud region distance158.6 mi

Site characteristics

Site typeGreenfield
Parcel ownerRobert & Barbara Solverson Irrevocable Trust
Land owner typeprivate
Buildability65.0/100
Land cover (NLCD)Cultivated Crops
Former usecoal adjacent

Risk & environment

Flood zoneZone X
Water stress (WRI)0.30
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score78/100
Construction cost index69.7 (avg 100)

Location context

Nearest datacenterDatacenter 1211362828
DC distance58.3 mi
Nearest rail16.0 mi
Nearest gas pipeline3.6 mi
Nearest fiber route79.4 mi
County hazard (FEMA NRI)Relatively Low (22)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.41¢/kWh
Industrial electricity9.00¢/kWh
Cooling degree days600
Heating degree days7,200
Land price / acre$5,236

Incentive detail: Enterprise Zone tax credits; TIF available for DC construction in eligible areas.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
47
Fiber connectivity12%
63
Energy cost10%
85
Water risk8%
94
Natural hazard8%
78
Buildability7%
65
Labor market4%
50
DC cluster4%
45
Land / acreage3%
47
Construction cost3%
92
Gas pipeline2%
88
Tax incentive2%
100
Climate / cooling2%
95

Nearby comparable sites

Other scored datacenter candidate sites in Vernon, ranked by DC Readiness.

Sites near EC Coal Vernon County
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN159041Substation-Adjacent161 kV100 MW1.4 yrs66.5
Greenfield (DPC BELL CENTER - UNKNOWN15904)Greenfield161 kV100 MW1.4 yrs63.2
EC Coal Vernon CountyGreenfield1.4 yrs61.5
EC Near GenoaGreenfield1.4 yrs59.8
OZ VernonGreenfield1.4 yrs59.3
EC Near GenoaGreenfield1.4 yrs58.2
EC Near GenoaGreenfield1.4 yrs58.1
EC Near GenoaGreenfield1.4 yrs57.6

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for EC Coal Vernon County, Vernon. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.