Datacenter Sites in Wood County, Wisconsin
Wood County has 57 scored datacenter candidate sites averaging 52.2/100 DC Readiness, with a catalogued aggregate of 3,679 MW. FEMA rates local natural-hazard risk as "Relatively Low". The county has a datacenter tax incentive on record.
57
Candidate sites
52.2/100
Avg DC Readiness
3,679 MW
Catalogued capacity
theoretical aggregate
Relatively Low
Hazard rating
Site-selection context for Wood County
Yessales_tax_exemption
Datacenter tax incentive
11.83¢/kWh
Commercial electricity
8.33¢/kWh
Industrial electricity
8
Fiber providers
Low
Water stress
$4,417
Land price / acre
600
Cooling degree days
7,200
Heating degree days
44°F
Mean annual temp
Incentive detail: Enterprise Zone tax credits; TIF available for DC construction in eligible areas.
By site type
Top datacenter sites in Wood County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| HUME | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 75.6 |
| MARSHFIELD UTILITIES GAS PLANT | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 72.8 |
| ARPIN | Substation-Adjacent | 345 kV | 600 MW | 1.4 yrs | 72.7 |
| Greenfield (UNKNOWN129869 - ARPIN) | Greenfield | 345 kV | 600 MW | 1.4 yrs | 72.6 |
| SIGEL | Substation-Adjacent | 138 kV | 100 MW | 1.4 yrs | 71.3 |
| SAND LAKE | Substation-Adjacent | 138 kV | 100 MW | 1.4 yrs | 70.7 |
| WILDWOOD (MEWD) | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 70.2 |
| BAKER ST | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 66.9 |
| LAKEHEAD VESPER | Substation-Adjacent | 138 kV | 100 MW | 1.4 yrs | 66.8 |
| MCMILLAN | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 66.3 |
| Greenfield (ARPIN - ROCKY RUN) | Greenfield | 345 kV | 600 MW | 1.4 yrs | 65.9 |
| Greenfield (ARPIN - ROCKY RUN) | Greenfield | 345 kV | 600 MW | 1.4 yrs | 65.6 |
| HOLLYWOOD | Substation-Adjacent | 138 kV | 100 MW | 1.4 yrs | 65.3 |
| Wisconsin Rapids Pulp Mill | Brownfield | — | 72 MW | 1.4 yrs | 63.5 |
| Greenfield (MARSHFIELD UTILITIES GAS PLANT) | Greenfield | 115 kV | 100 MW | 1.4 yrs | 61.8 |
| PORT EDWARDS | Substation-Adjacent | 138 kV | 100 MW | 1.4 yrs | 61.3 |
| TAP139562 | Substation-Adjacent | 138 kV | 100 MW | 1.4 yrs | 58.6 |
| EC Near Port Edwards Mill | Greenfield | — | — | 1.4 yrs | 57.2 |
| EC Near Port Edwards Mill | Greenfield | — | — | 1.4 yrs | 56.1 |
| OZ Wood | Greenfield | — | — | 1.4 yrs | 55.9 |
| Port Edwards Mill | Brownfield | — | 7 MW | 1.4 yrs | 55.4 |
| EC Near Port Edwards Mill | Greenfield | — | — | 1.4 yrs | 55.4 |
| EC Near Port Edwards Mill | Greenfield | — | — | 1.4 yrs | 54.9 |
| EC Near Port Edwards Mill | Greenfield | — | — | 1.4 yrs | 54.8 |
| EC Near Port Edwards Mill | Greenfield | — | — | 1.4 yrs | 52.7 |
Wood County datacenter FAQ
- How many datacenter sites are in Wood County?
- 57 scored datacenter candidate sites, averaging 52.2/100 DC Readiness.
- Does Wood County offer datacenter tax incentives?
- Enterprise Zone tax credits; TIF available for DC construction in eligible areas.
- What is the natural-hazard risk in Wood County?
- FEMA's National Risk Index rates Wood County as "Relatively Low" (score 22).
- What are industrial electricity rates in Wood County?
- Average industrial electricity is 8.33¢/kWh and commercial is 11.83¢/kWh in Wood County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Wood County, Wisconsin. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.