EC FFE Wexford County

Greenfield

Wexford County, Michigan · PJM

DC Readiness
61.5
Good / 100

EC FFE Wexford County is a greenfield datacenter candidate site in Wexford County, Michigan, interconnecting through PJM. It screens at 61.5/100 DC Readiness and a 2.2 yrs average interconnection-queue wait.

Power & interconnection

LMP zonePJM_ATSI
Wholesale LMP$42.97/MWh
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth11
Avg queue wait2.2 yrs
Recent queue wait2.2 yrs
Completion rate20%
Withdrawal rate80%

Connectivity

Nearest IXP123.NET - DC4 - 400 76th St SW
IXP distance104.6 mi
Fiber providers5
Fiber coverage34.2%
Nearest cloud providerAzure
Nearest cloud regionnorthcentralus
Cloud region distance199.0 mi

Site characteristics

Site typeGreenfield
Parcel ownerCONSUMERS ENERGY CO
Land owner typeprivate
Buildability90.0/100
Land cover (NLCD)Developed, Open Space
Former usefossil fuel employment

Risk & environment

Flood zoneZone X
Water stress (WRI)0.30
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score75/100
Construction cost index66.7 (avg 100)

Location context

Nearest datacenterManagedWay BYK1
DC distance104.6 mi
Nearest rail3.1 mi
Nearest gas pipeline8.1 mi
Nearest fiber route40.1 mi
County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity11.18¢/kWh
Industrial electricity7.16¢/kWh
Cooling degree days700
Heating degree days6,600
Land price / acre$3,918

Incentive detail: Personal property tax exemption for eligible DC equipment; MEGA tax credits.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
56
Fiber connectivity12%
58
Energy cost10%
82
Water risk8%
93
Natural hazard8%
75
Buildability7%
90
Labor market4%
50
DC cluster4%
20
Land / acreage3%
49
Construction cost3%
94
Gas pipeline2%
74
Tax incentive2%
100
Climate / cooling2%
90

Nearby comparable sites

Other scored datacenter candidate sites in Wexford County, ranked by DC Readiness.

Sites near EC FFE Wexford County
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN145744Substation-Adjacent138 kV100 MW2.2 yrs64.2
C W TIPPYSubstation-Adjacent138 kV100 MW2.2 yrs63.8
TAP145688Substation-Adjacent138 kV100 MW2.2 yrs61.3
Greenfield (TIPPY DAM - TAP145688)Greenfield138 kV100 MW2.2 yrs61.1
Greenfield (UNKNOWN145744 - KEYSTONE)Greenfield138 kV100 MW2.2 yrs60.9
Greenfield (UNKNOWN145744 - KEYSTONE)Greenfield138 kV100 MW2.2 yrs60.8
TIPPY DAMSubstation-Adjacent138 kV100 MW2.2 yrs60.1
Greenfield (KEYSTONE - LUDINGTON)Greenfield345 kV600 MW1.4 yrs60.1

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for EC FFE Wexford County, Wexford County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.