Datacenter Sites in Lyon, Minnesota
Lyon has 37 scored datacenter candidate sites averaging 54.0/100 DC Readiness, with a catalogued aggregate of 3,505 MW. FEMA rates local natural-hazard risk as "Relatively Moderate". The county has a datacenter tax incentive on record.
37
Candidate sites
54.0/100
Avg DC Readiness
3,505 MW
Catalogued capacity
theoretical aggregate
Relatively Moderate
Hazard rating
Site-selection context for Lyon
Yessales_tax_exemption
Datacenter tax incentive
11.48¢/kWh
Commercial electricity
7.77¢/kWh
Industrial electricity
8
Fiber providers
Low
Water stress
$7,146
Land price / acre
600
Cooling degree days
7,700
Heating degree days
42°F
Mean annual temp
Incentive detail: Sales tax exemption on DC equipment and electricity for qualified DCs.
By site type
Top datacenter sites in Lyon
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| LYON COUNTY | Substation-Adjacent | 345 kV | 600 MW | 1.0 yrs | 71.6 |
| UNKNOWN132582 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 67.4 |
| UNKNOWN132552 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 66.9 |
| Greenfield (LYON COUNTY - CEDAR MOUNTAIN) | Greenfield | 345 kV | 600 MW | 1.4 yrs | 66.2 |
| UNKNOWN132498 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 65.5 |
| Greenfield (BROOKINGS COUNTY - LYON COUNTY) | Greenfield | 345 kV | 600 MW | 1.0 yrs | 63.0 |
| EC Near Co Rd 33 | Greenfield | — | — | 1.4 yrs | 62.7 |
| MARSHALL (MN) | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 62.1 |
| Greenfield (UNKNOWN132498 - LYON COUNTY) | Greenfield | 115 kV | 100 MW | 1.4 yrs | 60.7 |
| UNKNOWN132549 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 60.5 |
| EC Near Co Rd 33 | Greenfield | — | — | 1.4 yrs | 60.4 |
| EC Near Co Rd 33 | Greenfield | — | — | 1.4 yrs | 60.3 |
| EC Near Co Rd 33 | Greenfield | — | — | 1.4 yrs | 59.8 |
| Greenfield (BROOKINGS COUNTY - LYON COUNTY) | Greenfield | 345 kV | 600 MW | 1.0 yrs | 59.7 |
| Greenfield (UNKNOWN132498 - LYON COUNTY) | Greenfield | 115 kV | 100 MW | 1.4 yrs | 58.4 |
| EC Near Co Rd 33 | Greenfield | — | — | 1.4 yrs | 58.2 |
| EC Near Co Rd 33 | Greenfield | — | — | 1.4 yrs | 57.6 |
| Greenfield (UNKNOWN132498 - LYON COUNTY) | Greenfield | 115 kV | 100 MW | 1.4 yrs | 57.4 |
| EC Near Co Rd 33 | Greenfield | — | — | 1.4 yrs | 57.3 |
| EC Near Co Rd 33 | Greenfield | — | — | 1.4 yrs | 56.8 |
| Greenfield (UNKNOWN132498 - LYON COUNTY) | Greenfield | 115 kV | 100 MW | 1.4 yrs | 56.6 |
| EC Near Co Rd 33 | Greenfield | — | — | 1.4 yrs | 56.4 |
| Greenfield (UNKNOWN132498 - LYON COUNTY) | Greenfield | 115 kV | 100 MW | 1.4 yrs | 55.4 |
| Greenfield (UNKNOWN132498 - LYON COUNTY) | Greenfield | 115 kV | 100 MW | 1.4 yrs | 53.6 |
| Co Rd 33 | Brownfield | — | 5 MW | 1.4 yrs | 51.8 |
Lyon datacenter FAQ
- How many datacenter sites are in Lyon?
- 37 scored datacenter candidate sites, averaging 54.0/100 DC Readiness.
- Does Lyon offer datacenter tax incentives?
- Sales tax exemption on DC equipment and electricity for qualified DCs.
- What is the natural-hazard risk in Lyon?
- FEMA's National Risk Index rates Lyon as "Relatively Moderate" (score 25).
- What are industrial electricity rates in Lyon?
- Average industrial electricity is 7.77¢/kWh and commercial is 11.48¢/kWh in Lyon.