Greenfield (UNKNOWN132498 - LYON COUNTY)

Greenfield

Lyon, Minnesota · MISO

DC Readiness
55.4
Good / 100

Greenfield (UNKNOWN132498 - LYON COUNTY) is a greenfield datacenter candidate site in Lyon, Minnesota, interconnecting through MISO. It screens at 55.4/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 1.4 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN132498
Substation voltage115 kV
Available capacity100 MW
LMP zoneMISO_MINN
Wholesale LMP$34.82/MWh
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionMISO
Queue depth16
Avg queue wait1.4 yrs
Recent queue wait1.4 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPTierPoint Sioux Falls - East
IXP distance73.7 mi
Fiber providers8
Fiber coverage14.0%
Nearest cloud providerGCP
Nearest cloud regionus-central1
Cloud region distance215.3 mi

Site characteristics

Site typeGreenfield
Parcel ownerOTTER TAIL POWER CO
Land owner typeprivate
Buildability20.0/100
Land cover (NLCD)Emergent Herbaceous Wetlands

Risk & environment

Flood zoneZone X
Water stress (WRI)0.40
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score75/100
Construction cost index84.0 (avg 100)

Location context

Nearest datacenterTierPoint Sioux Falls - East
DC distance73.7 mi
Nearest rail7.1 mi
Nearest gas pipeline6.6 mi
Nearest fiber route121.0 mi
County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.48¢/kWh
Industrial electricity7.77¢/kWh
Cooling degree days600
Heating degree days7,700
Land price / acre$7,146

Incentive detail: Sales tax exemption on DC equipment and electricity for qualified DCs.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
28
Speed to power15%
57
Fiber connectivity12%
50
Energy cost10%
87
Water risk8%
89
Natural hazard8%
75
Buildability7%
20
Labor market4%
50
DC cluster4%
20
Land / acreage3%
44
Construction cost3%
80
Gas pipeline2%
79
Tax incentive2%
100
Climate / cooling2%
95

Nearby comparable sites

Other scored datacenter candidate sites in Lyon, ranked by DC Readiness.

Sites near Greenfield (UNKNOWN132498 - LYON COUNTY)
SiteTypeVoltageCapacityQueue waitScore
LYON COUNTYSubstation-Adjacent345 kV600 MW1.0 yrs71.6
UNKNOWN132582Substation-Adjacent115 kV100 MW1.4 yrs67.4
UNKNOWN132552Substation-Adjacent115 kV100 MW1.4 yrs66.9
Greenfield (LYON COUNTY - CEDAR MOUNTAIN)Greenfield345 kV600 MW1.4 yrs66.2
UNKNOWN132498Substation-Adjacent115 kV100 MW1.4 yrs65.5
Greenfield (BROOKINGS COUNTY - LYON COUNTY)Greenfield345 kV600 MW1.0 yrs63.0
EC Near Co Rd 33Greenfield1.4 yrs62.7
MARSHALL (MN)Substation-Adjacent115 kV100 MW1.4 yrs62.1

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (UNKNOWN132498 - LYON COUNTY), Lyon. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.