DC Readiness
56.0
Good / 100

Kirksville is a brownfield datacenter candidate site in Adair, Missouri, interconnecting through MISO. It screens at 56.0/100 DC Readiness with a catalogued 15 MW of candidate capacity and a 1.4 yrs average interconnection-queue wait.

Power & interconnection

Available capacity15 MW
LMP zoneMISO_ILLINOIS
Wholesale LMP$33.26/MWh
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionMISO
Queue depth34
Avg queue wait1.4 yrs
Recent queue wait1.4 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPConnect Des Moines
IXP distance108.6 mi
Fiber providers5
Fiber coverage77.5%
Nearest cloud providerAzure
Nearest cloud regioncentralus
Cloud region distance117.3 mi

Site characteristics

Site typeBrownfield
Parcel ownerUnion Electric Co
Land owner typeprivate
Buildability95.0/100
Land cover (NLCD)Developed, Medium Intensity
Former usegas
Existing capacity15 MW
Retirement date2018-01-01

Risk & environment

Flood zoneZone X
Water stress (WRI)0.60
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteHOME DEPOT STORE 3036
Hazard sub-score52/100
Construction cost index76.1 (avg 100)

Location context

Nearest datacenterCenturyLink
DC distance81.8 mi
Nearest rail12.6 mi
Nearest gas pipeline25.7 mi
Nearest fiber route256.4 mi
County hazard (FEMA NRI)Relatively High (38)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.58¢/kWh
Industrial electricity7.49¢/kWh
Cooling degree days1,500
Heating degree days4,700
Land price / acre$4,098

Incentive detail: Qualified data center sales tax exemption (2019 law); state income tax credits.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
24
Speed to power15%
39
Fiber connectivity12%
62
Energy cost10%
89
Water risk8%
88
Natural hazard8%
52
Buildability7%
95
Labor market4%
50
DC cluster4%
25
Land / acreage3%
73
Construction cost3%
87
Gas pipeline2%
17
Tax incentive2%
100
Climate / cooling2%
50

Nearby comparable sites

Other scored datacenter candidate sites in Adair, ranked by DC Readiness.

Sites near Kirksville
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN117964Substation-Adjacent161 kV100 MW1.4 yrs64.8
EC Near KirksvilleGreenfield1.4 yrs57.8
EC Near KirksvilleGreenfield1.4 yrs57.2
EC Near KirksvilleGreenfield1.4 yrs56.9
La PlataBrownfield4 MW1.4 yrs56.9
EC Near KirksvilleGreenfield1.4 yrs56.7
OZ AdairGreenfield1.4 yrs56.5
EC Near KirksvilleGreenfield1.4 yrs56.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.