Cambridge

Brownfield

Furnas, Nebraska · SPP

DC Readiness
53.5
Fair / 100

Cambridge is a brownfield datacenter candidate site in Furnas, Nebraska, interconnecting through SPP. It screens at 53.5/100 DC Readiness with a catalogued 1 MW of candidate capacity and a 3.5 yrs average interconnection-queue wait.

Power & interconnection

Available capacity1 MW
LMP zoneSPP_NORTH
Wholesale LMP$21.13/MWh

Speed to power

ISO / RTO regionSPP
Queue depth31
Avg queue wait3.5 yrs
Recent queue wait3.5 yrs
Completion rate16%
Withdrawal rate84%

Connectivity

Nearest IXPBeloit-NOC
IXP distance123.6 mi
Fiber providers4
Fiber coverage72.4%
Nearest cloud providerGCP
Nearest cloud regionus-central1
Cloud region distance235.6 mi

Site characteristics

Site typeBrownfield
Parcel ownerCity of Cambridge
Land owner typeprivate
Buildability75.0/100
Former useoil
Existing capacity1 MW
Retirement date2005-03-01

Risk & environment

Flood zoneZone X
Water stress (WRI)2.00
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteCAMBRIDGE CO OP OIL
Hazard sub-score62/100
Construction cost index71.3 (avg 100)

Location context

Nearest datacenterCompute North
DC distance67.1 mi
Nearest rail0.5 mi
Nearest gas pipeline0.1 mi
Nearest fiber route210.9 mi
County hazard (FEMA NRI)Relatively Moderate (28)
DC tax incentiveYes (sales_tax_exemption)
Cooling degree days1,000
Heating degree days6,200
Land price / acre$2,895

Incentive detail: ImagiNE Nebraska Act: sales tax exemption on DC equipment; investment tax credits.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
23
Speed to power15%
33
Fiber connectivity12%
69
Energy cost10%
78
Water risk8%
60
Natural hazard8%
62
Buildability7%
75
Labor market4%
50
DC cluster4%
20
Land / acreage3%
60
Construction cost3%
91
Gas pipeline2%
100
Tax incentive2%
100
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in Furnas, ranked by DC Readiness.

Sites near Cambridge
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN131958Substation-Adjacent115 kV100 MW3.5 yrs63.6
EC Near CambridgeGreenfield3.5 yrs57.5
EC Near CambridgeGreenfield3.5 yrs57.4
EC Near CambridgeGreenfield3.5 yrs56.9
EC Near CambridgeGreenfield3.5 yrs56.4
EC Near CambridgeGreenfield3.5 yrs56.4
EC Near CambridgeGreenfield3.5 yrs56.3
EC Near CambridgeGreenfield3.5 yrs55.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Cambridge, Furnas. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.