Datacenter Sites in Camden County, New Jersey
Camden County has 105 scored datacenter candidate sites averaging 49.7/100 DC Readiness, with a catalogued aggregate of 8,104 MW. FEMA rates local natural-hazard risk as "Relatively Moderate". The county has a datacenter tax incentive on record.
105
Candidate sites
49.7/100
Avg DC Readiness
8,104 MW
Catalogued capacity
theoretical aggregate
Relatively Moderate
Hazard rating
Site-selection context for Camden County
Yessales_tax_exemption
Datacenter tax incentive
10.81¢/kWh
Commercial electricity
7.48¢/kWh
Industrial electricity
9
Fiber providers
Low
Water stress
$18,360
Land price / acre
1,000
Cooling degree days
4,900
Heating degree days
53°F
Mean annual temp
Incentive detail: UEZ sales tax exemption (reduced rate); BEIP/Grow NJ incentives for job creation.
By site type
Top datacenter sites in Camden County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| NEW FREEDOM | Substation-Adjacent | 500 kV | 1,000 MW | 3.0 yrs | 75.2 |
| BEAVER BROOK | Substation-Adjacent | 230 kV | 300 MW | 3.0 yrs | 75.0 |
| SICKLER | Substation-Adjacent | 230 kV | 300 MW | 3.0 yrs | 73.3 |
| SILVER LAKE | Substation-Adjacent | 230 kV | 300 MW | 3.0 yrs | 72.2 |
| MARLTON | Substation-Adjacent | 230 kV | 300 MW | 3.0 yrs | 71.2 |
| Greenfield (UNKNOWN132218 - NEW FREEDOM) | Greenfield | 500 kV | 1,000 MW | 3.1 yrs | 67.1 |
| Greenfield (NEW FREEDOM - BEAVER BROOK) | Greenfield | 230 kV | 300 MW | 3.0 yrs | 66.8 |
| Campbell's Soup #2 | Brownfield | — | 3 MW | — | 65.6 |
| OZ Camden | Greenfield | — | — | 2.6 yrs | 65.5 |
| Greenfield (ORCHARD STATION - NEW FREEDOM) | Greenfield | 500 kV | 1,000 MW | 3.0 yrs | 65.4 |
| Greenfield (UNKNOWN132218 - NEW FREEDOM) | Greenfield | 500 kV | 1,000 MW | 3.1 yrs | 65.3 |
| Greenfield (NEW FREEDOM - HOPE CREEK) | Greenfield | 500 kV | 1,000 MW | 3.1 yrs | 65.1 |
| Greenfield (MARLTON - NEW FREEDOM) | Greenfield | 230 kV | 300 MW | 3.0 yrs | 64.5 |
| Campbell's Soup #1 | Brownfield | — | 2 MW | — | 64.4 |
| Greenfield (EAST WINDSOR - NEW FREEDOM) | Greenfield | 500 kV | 1,000 MW | 3.0 yrs | 64.1 |
| OZ Camden | Greenfield | — | — | 2.6 yrs | 59.7 |
| OZ Camden | Greenfield | — | — | 2.6 yrs | 58.9 |
| Greenfield (NEW FREEDOM - CARDIFF) | Greenfield | 230 kV | 300 MW | 3.0 yrs | 58.4 |
| Aabco Barrel Site (Abc) | Industrial | — | — | — | 46.9 |
| Former RCA Building 8 | Industrial | — | — | — | 46.9 |
| Banteviglio & Sons | Industrial | — | — | — | 46.9 |
| William Bryen/Bryen Meats Site | Industrial | — | — | — | 46.9 |
| Block N/Woolworth Site | Industrial | — | — | — | 46.8 |
| Borden Chemical | Industrial | — | — | — | 46.8 |
| Waterfront South Service Station | Industrial | — | — | — | 46.8 |
Camden County datacenter FAQ
- How many datacenter sites are in Camden County?
- 105 scored datacenter candidate sites, averaging 49.7/100 DC Readiness.
- Does Camden County offer datacenter tax incentives?
- UEZ sales tax exemption (reduced rate); BEIP/Grow NJ incentives for job creation.
- What is the natural-hazard risk in Camden County?
- FEMA's National Risk Index rates Camden County as "Relatively Moderate" (score 28).
- What are industrial electricity rates in Camden County?
- Average industrial electricity is 7.48¢/kWh and commercial is 10.81¢/kWh in Camden County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Camden County, New Jersey. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.