Greenfield (UNKNOWN132619 - BRANCHBURG)

Greenfield

Morris County, New Jersey · PJM

DC Readiness
69.5
Good / 100

Greenfield (UNKNOWN132619 - BRANCHBURG) is a greenfield datacenter candidate site in Morris County, New Jersey, interconnecting through PJM. It screens at 69.5/100 DC Readiness with a catalogued 1,000 MW of candidate capacity and a 3.0 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN132619
Substation voltage500 kV
Available capacity1,000 MW
LMP zonePJM_PECO
Wholesale LMP$38.56/MWh
Utility commercial rate0.10¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth411
Avg queue wait3.0 yrs
Recent queue wait1.6 yrs
Completion rate19%
Withdrawal rate81%

Connectivity

Nearest IXPPlanet Networks Newton Datacenter
IXP distance10.8 mi
Fiber providers14
Fiber coverage94.4%
Nearest cloud providerAWS
Nearest cloud regionus-east-1
Cloud region distance194.5 mi

Site characteristics

Site typeGreenfield
Parcel ownerJERSEY CENTRAL POWER & LT CO
Land owner typeprivate
Buildability75.0/100
Land cover (NLCD)Pasture/Hay

Risk & environment

Flood zoneZone X
Water stress (WRI)0.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteFEDERAL EXPRESS CORP
Hazard sub-score62/100
Construction cost index118.9 (avg 100)

Location context

Nearest datacenterPlanet Networks Newton Datacenter
DC distance10.8 mi
Nearest rail0.6 mi
Nearest gas pipeline1.2 mi
Nearest fiber route104.9 mi
County hazard (FEMA NRI)Relatively Moderate (28)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity9.56¢/kWh
Industrial electricity8.27¢/kWh
Cooling degree days1,000
Heating degree days4,900
Land price / acre$30,022

Incentive detail: UEZ sales tax exemption (reduced rate); BEIP/Grow NJ incentives for job creation.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
72
Speed to power15%
42
Fiber connectivity12%
83
Energy cost10%
81
Water risk8%
88
Natural hazard8%
62
Buildability7%
75
Labor market4%
50
DC cluster4%
80
Land / acreage3%
45
Construction cost3%
51
Gas pipeline2%
96
Tax incentive2%
100
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in Morris County, ranked by DC Readiness.

Sites near Greenfield (UNKNOWN132619 - BRANCHBURG)
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN132392Substation-Adjacent230 kV300 MW3.0 yrs75.2
UNKNOWN132944Substation-Adjacent230 kV300 MW3.5 yrs70.3
UNKNOWN132619Substation-Adjacent500 kV1,000 MW3.5 yrs69.5
Greenfield (UNKNOWN132619 - BRANCHBURG)Greenfield500 kV1,000 MW3.0 yrs68.8
UNKNOWN132302Substation-Adjacent230 kV300 MW3.0 yrs68.3
UNKNOWN132303Substation-Adjacent230 kV300 MW3.5 yrs67.8
Greenfield (PORTLAND STATION - UNKNOWN1636)Greenfield230 kV300 MW3.0 yrs67.1
Greenfield (UNKNOWN132619 - BRANCHBURG)Greenfield500 kV1,000 MW3.0 yrs66.5

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Greenfield (UNKNOWN132619 - BRANCHBURG), Morris County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.