Datacenter Sites in Seneca, New York

Seneca has 23 scored datacenter candidate sites averaging 53.9/100 DC Readiness, with a catalogued aggregate of 1,006 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.

23
Candidate sites
53.9/100
Avg DC Readiness
1,006 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating

Site-selection context for Seneca

Yessales_tax_exemption
Datacenter tax incentive
9.87¢/kWh
Commercial electricity
7.32¢/kWh
Industrial electricity
7
Fiber providers
Low
Water stress
$4,610
Land price / acre
700
Cooling degree days
6,100
Heating degree days
46°F
Mean annual temp

Incentive detail: Excelsior Jobs Program tax credits; IDA property tax abatements (PILOT); Empire State Digital Gaming.

By site type

Top datacenter sites in Seneca

Top datacenter sites in Seneca
SiteTypeVoltageCapacityQueue waitScore
GUARDIAN GLASSSubstation-Adjacent115 kV100 MW3.5 yrs62.4
HAMILTON RDSubstation-Adjacent115 kV100 MW3.5 yrs61.0
GENEVA BORDER CITYSubstation-Adjacent115 kV100 MW3.5 yrs59.9
CAYUGA OPERATING COMPANYSubstation-Adjacent115 kV100 MW3.5 yrs59.3
WRIGHT AVENUESubstation-Adjacent115 kV100 MW3.5 yrs57.8
Greenfield (GUARDIAN GLASS - UNKNOWN125140)Greenfield115 kV100 MW3.5 yrs57.3
UNKNOWN125140Substation-Adjacent115 kV100 MW3.5 yrs56.5
Greenfield (UNKNOWN124194 - UNKNOWN125140)Greenfield115 kV100 MW3.5 yrs56.0
Greenfield (GENEVA BORDER CITY - TAP167223)Greenfield115 kV100 MW3.5 yrs55.2
EC Near Seneca EnergyGreenfield3.5 yrs55.1
EC Near Seneca EnergyGreenfield3.5 yrs54.5
EC Near Seneca EnergyGreenfield3.5 yrs54.5
EC Coal Seneca CountyGreenfield3.5 yrs54.1
Greenfield (CAYUGA OPERATING COMPANY - WRI)Greenfield115 kV100 MW3.5 yrs54.0
EC Near Seneca EnergyGreenfield3.5 yrs53.9
EC FFE Seneca CountyGreenfield3.5 yrs51.7
EC Near Seneca EnergyGreenfield3.5 yrs50.8
EC Near Seneca EnergyGreenfield3.5 yrs50.7
EC Near Seneca EnergyGreenfield3.5 yrs50.7
EC Near Seneca EnergyGreenfield3.5 yrs49.8
Seneca EnergyBrownfield6 MW3.5 yrs47.6
OZ SenecaGreenfield3.5 yrs46.2
Mine SiteFormer Mine41.1

Seneca datacenter FAQ

How many datacenter sites are in Seneca?
23 scored datacenter candidate sites, averaging 53.9/100 DC Readiness.
Does Seneca offer datacenter tax incentives?
Excelsior Jobs Program tax credits; IDA property tax abatements (PILOT); Empire State Digital Gaming.
What is the natural-hazard risk in Seneca?
FEMA's National Risk Index rates Seneca as "Relatively High" (score 35).
What are industrial electricity rates in Seneca?
Average industrial electricity is 7.32¢/kWh and commercial is 9.87¢/kWh in Seneca.

Dataset updated . Screening estimates derived from public data sources.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Seneca, New York. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.