EC Coal Clinton County

Greenfield

Clinton, Pennsylvania · PJM

DC Readiness
51.6
Fair / 100

EC Coal Clinton County is a greenfield datacenter candidate site in Clinton, Pennsylvania, interconnecting through PJM. It screens at 51.6/100 DC Readiness and a 3.0 yrs average interconnection-queue wait.

Power & interconnection

LMP zonePJM_PECO
Wholesale LMP$38.56/MWh
Utility commercial rate0.08¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth411
Avg queue wait3.0 yrs
Recent queue wait1.6 yrs
Completion rate19%
Withdrawal rate81%

Connectivity

Nearest IXPWindstream - State College
IXP distance29.9 mi
Fiber providers4
Fiber coverage8.8%
Nearest cloud providerAWS
Nearest cloud regionus-east-1
Cloud region distance138.9 mi

Site characteristics

Site typeGreenfield
Parcel ownerPPL ELECTRIC UTILITIES CORP
Land owner typeprivate
Buildability50.0/100
Former usecoal adjacent

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteCRODA INC
Hazard sub-score62/100
Construction cost index75.8 (avg 100)

Location context

Nearest datacenterWindstream - State College
DC distance29.9 mi
Nearest rail4.0 mi
Nearest gas pipeline2.9 mi
Nearest fiber route33.1 mi
County hazard (FEMA NRI)Relatively Moderate (28)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity8.43¢/kWh
Industrial electricity6.15¢/kWh
Cooling degree days800
Heating degree days5,600
Land price / acre$8,278

Incentive detail: Keystone Opportunity Zone/KOEZ sales and property tax exemptions in designated areas.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power15%
42
Fiber connectivity12%
9
Energy cost10%
85
Water risk8%
86
Natural hazard8%
62
Buildability7%
50
Labor market4%
50
DC cluster4%
65
Land / acreage3%
57
Construction cost3%
87
Gas pipeline2%
91
Tax incentive2%
100
Climate / cooling2%
85

Nearby comparable sites

Other scored datacenter candidate sites in Clinton, ranked by DC Readiness.

Sites near EC Coal Clinton County
SiteTypeVoltageCapacityQueue waitScore
TAP140646Substation-Adjacent230 kV300 MW3.0 yrs67.2
UNKNOWN123586Substation-Adjacent230 kV300 MW3.0 yrs66.3
Greenfield (HOMER CITY - UNKNOWN171927)Greenfield345 kV600 MW3.0 yrs65.3
Greenfield (HOMER CITY - UNKNOWN171927)Greenfield345 kV600 MW3.0 yrs64.8
Greenfield (HOMER CITY - UNKNOWN171927)Greenfield345 kV600 MW3.0 yrs64.6
CHAPMANSubstation-Adjacent230 kV300 MW3.0 yrs64.1
Greenfield (HOMER CITY - UNKNOWN171927)Greenfield345 kV600 MW3.0 yrs62.2
TAP138433Substation-Adjacent230 kV300 MW3.0 yrs61.8

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.