Datacenter Sites in Clinton, Pennsylvania

Clinton has 34 scored datacenter candidate sites averaging 50.3/100 DC Readiness, with a catalogued aggregate of 4,520 MW. FEMA rates local natural-hazard risk as "Relatively Moderate". The county has a datacenter tax incentive on record.

34
Candidate sites
50.3/100
Avg DC Readiness
4,520 MW
Catalogued capacity
theoretical aggregate
Relatively Moderate
Hazard rating

Site-selection context for Clinton

Yessales_tax_exemption
Datacenter tax incentive
8.43¢/kWh
Commercial electricity
6.15¢/kWh
Industrial electricity
4
Fiber providers
Low
Water stress
$8,278
Land price / acre
800
Cooling degree days
5,600
Heating degree days
50°F
Mean annual temp

Incentive detail: Keystone Opportunity Zone/KOEZ sales and property tax exemptions in designated areas.

By site type

Top datacenter sites in Clinton

Top datacenter sites in Clinton
SiteTypeVoltageCapacityQueue waitScore
TAP140646Substation-Adjacent230 kV300 MW3.0 yrs67.2
UNKNOWN123586Substation-Adjacent230 kV300 MW3.0 yrs66.3
Greenfield (HOMER CITY - UNKNOWN171927)Greenfield345 kV600 MW3.0 yrs65.3
Greenfield (HOMER CITY - UNKNOWN171927)Greenfield345 kV600 MW3.0 yrs64.8
Greenfield (HOMER CITY - UNKNOWN171927)Greenfield345 kV600 MW3.0 yrs64.6
CHAPMANSubstation-Adjacent230 kV300 MW3.0 yrs64.1
Greenfield (HOMER CITY - UNKNOWN171927)Greenfield345 kV600 MW3.0 yrs62.2
TAP138433Substation-Adjacent230 kV300 MW3.0 yrs61.8
Greenfield (TAP138433 - TAP140646)Greenfield230 kV300 MW3.0 yrs60.6
Greenfield (HOMER CITY - UNKNOWN171927)Greenfield345 kV600 MW3.0 yrs58.5
EC Coal Clinton CountyGreenfield3.0 yrs57.0
EC Coal Clinton CountyGreenfield3.0 yrs56.4
EC FFE Clinton CountyGreenfield3.0 yrs55.6
Jersey Shore Steel CoBrownfield2 MW3.0 yrs54.9
OZ ClintonGreenfield3.0 yrs53.5
TalenEnergy Martins Creek LLC Lock HavenBrownfield19 MW3.0 yrs53.5
EC Coal Clinton CountyGreenfield3.0 yrs51.6
Mine SiteFormer Mine42.7
Mine SiteFormer Mine42.5
Mine SiteFormer Mine42.3
Mine SiteFormer Mine42.3
Mine SiteFormer Mine42.2
Mine SiteFormer Mine41.9
Renovo Industrial ParkIndustrial41.6
Mine SiteFormer Mine41.6

Clinton datacenter FAQ

How many datacenter sites are in Clinton?
34 scored datacenter candidate sites, averaging 50.3/100 DC Readiness.
Does Clinton offer datacenter tax incentives?
Keystone Opportunity Zone/KOEZ sales and property tax exemptions in designated areas.
What is the natural-hazard risk in Clinton?
FEMA's National Risk Index rates Clinton as "Relatively Moderate" (score 28).
What are industrial electricity rates in Clinton?
Average industrial electricity is 6.15¢/kWh and commercial is 8.43¢/kWh in Clinton.

Dataset updated . Screening estimates derived from public data sources.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Clinton, Pennsylvania. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.