Datacenter Sites in Fayette County, Pennsylvania
Fayette County has 274 scored datacenter candidate sites averaging 45.6/100 DC Readiness, with a catalogued aggregate of 12,200 MW. FEMA rates local natural-hazard risk as "Relatively Moderate". The county has a datacenter tax incentive on record.
274
Candidate sites
45.6/100
Avg DC Readiness
12,200 MW
Catalogued capacity
theoretical aggregate
Relatively Moderate
Hazard rating
Site-selection context for Fayette County
Yessales_tax_exemption
Datacenter tax incentive
12.33¢/kWh
Commercial electricity
9.84¢/kWh
Industrial electricity
13
Fiber providers
Low
Water stress
$7,064
Land price / acre
800
Cooling degree days
5,600
Heating degree days
50°F
Mean annual temp
Incentive detail: Keystone Opportunity Zone/KOEZ sales and property tax exemptions in designated areas.
By site type
Top datacenter sites in Fayette County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| UNKNOWN171935 | Substation-Adjacent | 500 kV | 1,000 MW | 3.0 yrs | 76.8 |
| RONCO | Substation-Adjacent | 500 kV | 1,000 MW | 3.0 yrs | 72.9 |
| Greenfield (HATFIELD - UNKNOWN171935) | Greenfield | 500 kV | 1,000 MW | 3.0 yrs | 69.6 |
| WESTRAVER | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 69.5 |
| Greenfield (HATFIELD - BLACK OAK) | Greenfield | 500 kV | 1,000 MW | 3.0 yrs | 68.5 |
| UNKNOWN157649 | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 68.5 |
| UNKNOWN124595 | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 68.2 |
| UNKNOWN123900 | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 68.2 |
| UNKNOWN124592 | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 68.0 |
| Greenfield (HATFIELD - UNKNOWN171935) | Greenfield | 500 kV | 1,000 MW | 3.0 yrs | 67.7 |
| UNKNOWN124594 | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 67.2 |
| HATFIELD | Substation-Adjacent | 500 kV | 1,000 MW | 3.0 yrs | 67.1 |
| Greenfield (HATFIELD - BLACK OAK) | Greenfield | 500 kV | 1,000 MW | 3.0 yrs | 66.9 |
| TAP171745 | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 66.9 |
| NECESSITY | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 66.6 |
| IRON BRIDGE | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 66.3 |
| UNKNOWN171747 | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 65.9 |
| Greenfield (HATFIELD - BLACK OAK) | Greenfield | 500 kV | 1,000 MW | 3.0 yrs | 65.6 |
| TAP140066 | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 65.2 |
| CONNELLSVILLE | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 65.1 |
| TAP140067 | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 65.1 |
| TAP140063 | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 64.9 |
| BETHELBORO | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 64.5 |
| UNKNOWN171749 | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 64.4 |
| Greenfield (HATFIELD - UNKNOWN171935) | Greenfield | 500 kV | 1,000 MW | 3.0 yrs | 63.5 |
Fayette County datacenter FAQ
- How many datacenter sites are in Fayette County?
- 274 scored datacenter candidate sites, averaging 45.6/100 DC Readiness.
- Does Fayette County offer datacenter tax incentives?
- Keystone Opportunity Zone/KOEZ sales and property tax exemptions in designated areas.
- What is the natural-hazard risk in Fayette County?
- FEMA's National Risk Index rates Fayette County as "Relatively Moderate" (score 28).
- What are industrial electricity rates in Fayette County?
- Average industrial electricity is 9.84¢/kWh and commercial is 12.33¢/kWh in Fayette County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Fayette County, Pennsylvania. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.